For faster services, inquiry about  new assignments submission or  follow ups on your assignments please text us/call us on +1 (251) 265-5102

WhatsApp Widget

49002 Managing Projects – Assignment 2

Faculty of Engineering & Information Technology 

49002 Managing Projects – Assignment 2 

49002 Managing Projects  COVER SHEET for Final Report of Group ASSIGNMENT  
By signing this form and submitting the attached report, I certify that this assignment is my and group members own work, based on our personal study and/or research, and we have acknowledged all material and sources in the preparation of the assignment.  We all certify that the assignment has not previously been submitted for assessment in any other course or at any other time in the same course and that we have not copied in part or whole or other-wise plagiarized work of others. We all agree and accept the % contribution of each member of the group as listed below. 
 Group Number 29 Date 11/10/2019
13420219  Mohan Sai Santosh Ayyala 
13395001  Rowin D’souza 
13662933  Rushi Dadhania 
13666336  Sarbartha Goswami 
13682683 Shravani Priya 

Date submitted: 11/10/2019 

Document Version: 2.2

Table of Contents

1 Introduction 5

Overview 5

Key Milestones 5

2 Stakeholder 6

Background 6

Stakeholder register 6

Stakeholder prioritisation grid 8

Stakeholder Communication Plan 10

3 Scope Statement 12

Background and rationale 12

Objectives, Goals, Needs 12

Assumptions 13

In-scope work and Out-of-scope work 14

In-Scope work 14

Out-of-Scope work 14

Deliverable 15

Milestones 15

External Dependencies 16

Limits and Exclusion 16

4 Work Breakdown Structure (WBS) 17

Background 17

Hierarchy 17

5 Network Diagram 20

Background 20

Network Diagram 20

Gantt Chart 20

6 Risk Management 21

Background and rationale 21

Risk Register 21

Risk Treatment Plan 26

7 Histogram of Resources 30

Background 30

Human Resource List 30

Resource Levelling (Human Resource) 32

Non-Human Resource List 35

Resource Levelling (Non-Human Resource) 40

8 Cost 43

Background 43

Cost summary 43

S-Curve 43

Cost table 44

Cumulative Cost Table 47

References 48

Appendix 48

Appendix 1: Version Control 48

Appendix 2: Gantt Chart 50

Appendix 3: Network Diagram 51

Appendix 4: WBS diagram 52

List of tables

Table 1: Stakeholder Register

Table 2: Stakeholder power and interest matrix

Table 3: Stakeholder Communication Plan

Table 4: Milestones

Table 5: WBS Coding

Table 6: Likelihood description

Table 7: Consequence description

Table 8: Risk Matrix

Table 9: Risk Register

Table 10: Risk Treatment Plan

Table 11: Human Resource List

Table 12: Human activities to be levelled

Table 13: Human resources needed each day

Table 14: After levelling of human Resources

Table 15: Non-Human Resource List

Table 16: Non-Human activities to be levelled

Table 17: Non-human resources needed each day

Table 18: After Levelling of non-human resources

Table 19: Cost table summary

Table 20: Cost Table

Table 21: Cumulative Cost Table

1 Introduction

This report is a proposal for our project management plan for constructing a house for the Jones family in Forster, NSW. Our Blue Bricks consultancy very interested in taking up the project and provide quality services to our client. The project is proposed to be completed within approximately twenty-one weeks and the estimated cost of the project is 1,088,645.49 AUD.

The knowledge areas mentioned in Project Management Book of Knowledge (PMBoK) were considered while developing this project plan report. This document is a reference to how to execute to the plan and will act as a validation sheet for cross checking.

Overview

Project Start Date: 28th October 2019

Project End Date: 16th April 2020

Total cost of the project: $ 1,089,645.49

Key Milestones

The key milestones are as follows:

  1. Completion of initial activities
  2. Completion of foundation work
  3. Completion of external work
  4. Completion of internal work
  5. Completion of installation of appliances and fitting
  6. Completion of final inspection and closure

2 Stakeholder 

Background 

Managing projects comprises of numerous roles out of which stakeholder management is one the most important aspects. Project management involves planning, organizing, delegating and controlling throughout the project lifecycle including managing involved parties with a stake. Stakeholders are defined as “Any group or individual who can affect or is affected by the achievement of the organizations objectives” (Freeman 1984, p. 46). Stakeholders will directly or indirectly affect the progress of the project, where the affect can be either positive or negative in nature. Implications include cost overruns, more lead time for project completion and may lead to project failure. 

“Stakeholders are individuals, groups or institutions with an interest in the project, and who can affect the outcome” (Boddy and Paton 2004). Any skilled person, operational or managerial, that is involved with the project requirements could affect the development process. Interest of some stakeholders are in line with the organisation’s goals. On the other hand, interests of some stakeholders are not in line with organisation’s goals. In conclusion, stakeholders play curial role in the success or failure of an organisation (Gibson 2000). 

Stakeholder register 

A project manager needs to create and maintain a record of all the stakeholders to efficiently keep track of the project. The project manager needs to ensure the progress is in line with the stakeholder’s requirements. It is crucial to discuss the requirements of each stakeholder before executing the project and keep a record based on priority and influence. The stakeholder register for our project provides basic information and tells about the type of each stakeholder. 

Table 1: Stakeholder Register

ID Information Assessment Information Classification
Stakeholder name/ position Contact Role in project Major requirements/ expectation Potential influence Internal/External Supporter/Neutral/ Resistor
Mr and Mrs Jones  Email ID
Customer  Handover of project within agreed time, cost and high quality.  Maximum  Internal  Supporter 
Mid-Coast Council  Council@midcoast.nsw.gov.au  Local regulatory authority  Maintaining conformance to the approved design plans during construction and planning of the project.  Maximum  External  Neutral 
 
  Designer
  

Email ID  
    Designer     Conformance to approved design plans.  – Timely communication of any design change requirement before implementation.                  Moderate        Internal        Neutral 
Stakeholder name/ position Contact Role in Project Major Requirement Potential Influence Internal / External Supporter/Neutral/Resistor
Bank  Email ID Financer  Completion of project within agreed budget.  Moderate  External  Supporter
Helen Aitken   Helen.Aitken@uts.edu.au Consultant  Clear and on time communication about the task with all relevant information about the required documents.  Minimal  Internal  Neutral 
Labour  contractor    Email ID
Labour  contractor  Effective management of manpower to support construction activity to reduce project delay time.  Moderate  Internal  Supporter 
Plumber    Email ID
Plumber  Completion and start of the work within agreed time.  Moderate  Internal  Neutral 
Electrician  Email ID Electrician  Completion and start of the work within agreed time.    Moderate  Internal  Neutral 
Painter    Email ID Painter  Completion and start of the work within agreed time.    Moderate  Internal  Neutral 
Supplier    Email ID
Supplier  Supply of correct quantity and conformance to delivery schedule.  Minimal  External  Neutral 
Local Community  In Person Meetings  Neighbours Completion of work within disturbance to the local community and reduction of noise, dust and undesirable effects from the construction activities.  Minimal  External  Neutral 

Stakeholder prioritisation grid 

Stakeholder priortisation grid is needed to be created because it is very important to classify stakeholder according to their power and interest in the project. The agenda of each stakeholder is different is so their decision-making power. The power and interest matrix identifies and differentiates the value of each stakeholder based on ratings (1-5). The stakeholder with minimum interest and power is rated ‘1’ and stakeholders with highest interest and power are rated ‘5’. 

The grid is further classified into four quadrants which shows the classification of stakeholders according to their power and interest. stakeholders who needs to be monitor is shown in the bottom left quadrant as they have less interest and power in the project. In upper left quadrant shows the stakeholders who needs to be kept satisfied as they have high power and less interest in the project. The stakeholders in bottom right quadrant has less interest and power but they are need kept informed as they are important for project. Upper right quadrant shows stakeholders who needs to be manage closely as they have more power and interest in the project. This grid helps the project manager to develop a communication method and maintain effective communication based on importance. 

No. Stakeholder Power (1-5) Interest (1-5)
Customer 
Local Regulatory Body 
Designer 
Financer 
Consultant 
Labour Contractor 
Plumber 
Electrician 
Painter 
10  Supplier 
11  Local Community 

Table 2: Stakeholder Power and Interest Matrix 

Figure 1: Stakeholder Power and Interest Grid 

Stakeholder Communication Plan 

Stakeholder Communication Plan is based on stakeholder prioritisation plan.  It is a table that tells the communication strategy corresponding to each stakeholder. 

Table 3: Stakeholder Communication Plan

SR. No. Communication Type Description Frequency Format Involved Parties Action Plan Responsible Individual
1 Initial meeting Discussion with local community regarding project. Once Face to Face meeting Project Manager, Neighbours Register the concerns Project manager
2
Task Monitoring


Discussion of completed, pending, and future tasks Weekly In Person/ Conference Call/ Email Project manager, Department Representatives Update Project Status Project manager
3 Community Announcements Intimating local community about any changes in project plan As per requirement Face to Face meeting Project Manager, Neighbours Register the concerns Project manager
4 Team Meeting Discussion of project status and further plan of action Weekly In person or conference call Project manager, Department Representatives Updating status register, and Requirements Project manager
5 Resource Requirement Meeting Comparison of various supplier quotes and price negotiation Once with individual vendor In person / mail / conference call
Procurement Head, Suppliers Finalising quotes and generating invoices Project manager and Procurement Head
6 Change-point Meeting Discussion of unplanned changes As per requirement In Person / Conference Call Project manager, Department Representatives Updating status register Project manager
7 Site meeting Discussion of activity related with site members As per requirement In person Site supervisor Discussion of work instruction and inspection sheet Site supervisor and Project manager
8 Task Progress Report Workflow monitoring and modification Daily In Person / on call Site supervisor Tracking Project Progress Project manager
9 Task Progress Report Workflow monitoring and modification Daily In Person/Telephone Project Manager Summarized report Consultant
10 Overall Task Progress Report Workflow monitoring and modification Every last working day of the week Email Project Manager Collecting information and documentation Mr and Mrs Jones, Helen Aitken

3 Scope Statement

Background and rationale 

Project scope clearly gives an understanding of the end stage or result of our project (Larson et al. 2013) and the purpose of this activity is to define the project face to end-users and create a project plan accordingly. Scope management of the project refers to the processes which will make sure a project’s scope is defined and mapped accurate. It further has methods which will assign proper amount of work necessary to effectively complete a project, also concerned with controlling what is part of project’s scope or not. The scope of our project is to properly bifurcate the tasks which are part of the project and which are not, along with scheduling the tasks according to the milestones giving it specific deadline to complete the project in the given duration. 

Scope management is a vital activity that should be carried out by every project manager to avoid confusion among stakeholders and eliminate project delays. Clearly defining the scope will ensure quality and cost effectiveness of all the activities related to project management.

The scope statement for the Jones villa project will identify goals, deliverables, milestones, technical requirements, limitations and exclusions. This can be used as a reference to any modifications, inclusions, and exclusions from the project. Not having a well-defined scope can lead to many problems like miscommunication, delays in deliverables, increase in cost or possible failure to complete project.

Objectives, Goals, Needs 

The main objective of our project is to construct a house which is fulfilling all the requirements of the owner in the given time and budget allocated to the project. In addition, it will be built according to the Australian Building code. The objectives clearly identify and quantify the resources required, skilled or unskilled labour and basis for overall construction along with interdependent activities and timely completion of the tasks.

The following are our goals

  1. Build a house of 252.74 m2 area in Forster Grange, NSW, Australia. Forster is in one of the precincts under the mid-coast council.
  2. Develop a project proposal considering the lump sum amount set by the Jones family.
  3. Design a roof trusses type house with 3m high walls and windows 2.1m x 0.9m.
  4. Design and build a house which confirms to external and internal requirements provided by the clients.
  5. Procure all the kitchen, bathroom, laundry and any electrical appliances as mentioned by the client during the agreement and planning stage.
  6. Ensure safety and quality inspections at every stage to ensure overall quality of the project.
  7. Handover the fully completed and inspected house within the projected time frame along with the review report.

Assumptions

An Assumption is something that is considered by default without any evidence. In an ideal case during project planning, all the information related to project phases is available before hand and project manager can make accurate predictions related to health of the project. Although, this may not be true for real world scenarios. Project managers need to fix certain variable like cost related to resources, manpower and scheduling. Project management team can get a better understanding of risk associated with the project by brainstorming assumptions that are relevant. Also the impact related to not confirming to the assumptions can be analysed beforehand and action plans can be created to mitigate the effects.

Assumptions can be good or bad depending on the affect they have on the project. It is always better to clarify or recheck with the clients and other involved parties to avoid any confusion or mismanagement. Impacts of these assumptions not holding true are categorised into four categories such as low, medium, high, and severe.

The following are the assumptions made during developing the project proposal

  1. The technical and non-technical specifications do not change during project execution (Impact level: High)
  2. The scope defined during project initiation stage does not change throughout the project lifecycle (Impact level: High).
  3. Cost related to the project and stakeholders would be paid and reimbursed as per project plan and agreements (Impact level: Medium).
  4. The resources for house construction would be procured as per project schedule (Impact level: High).
  5. Skilled and unskilled manpower would be assigned as per project needs to avoid excessive costs or delays (Impact level: Medium).
  6. Rules and regulations set by the mid-coast council do not change throughout the project lifecycle (Impact level: Low)
  7. There will be no interruption in project workflow by weather conditions, natural calamities like floods, bushfire during execution stage (Impact level: Severe).
  8. A well organised guidelines and systems for waste management from the construction site is already set up and in action. (Impact level: medium)
  9. We already have a clearance certificate from the government to build the house. (Impact level: Low)

In-scope work and Out-of-scope work

Setting boundaries for any project is a vital part of the project management. This boundary differentiates work into two categories such as in-scope and out-0f-scope work. Identification of these categories assists project managers to focus or direct their resources into relevant activities. Moreover, this helps in eliminating resource utilisation for unrelated activities.

In-Scope work

  1. Assessing and examining the plot for soil properties related to construction within the Forster Grange.
  2. Getting approvals and legal clearance from the local regulatory bodies.
  3. Performing site preparation, levelling or fill-up for constructions for initial foundation work.
  4. Setting up provisions for electrical and plumbing work during the foundation stage.
  5. Construction of external framework and clay brickwork along with roof trusses as per approved plan requirement.
  6. Ordering resources and arranging manpower, raw materials for construction activities as per agreed plan.
  7. Arranging necessities for construction such as electricity and water.
  8. Pre and post inspection of in-house work and subcontracted work to ensure conformance to the approved plan.
  9. Installation of “Gainsborough” keyed locks for front and rear doors along with security locks for other doors and windows.
  10. Constructing internal structure and furnishing as per agreement with the clients.

Out-of-Scope work

  1. Drafting layout plan and floor heightening
  2. Designing and setting up Air-conditioning system
  3. Landscaping activities like gardening and swimming pool construction
  4. Building a boundary or fence around the plot.

Deliverable

Deliverables are documents/necessities that are essential for keeping the client updated throughout the execution of project. Deliverables can be classified into two categories such as recurring deliverables and sign-off deliverables. Recurring deliverables are the ones used as a basis for measuring and controlling the progress of project outcomes like activities, or milestones. These are periodically submitted to the client or the relevant parties. Sigh-off deliverables are documents or amenities that are agreed upon by the client during the initial contract and are to be submitted only once.

Recurring Deliverables

  • Layout drawings and documents
  • Site analysis report
  • Regulatory body approval documents
  • Invoices for the resources
  • Status report of the progress in the project

Sign-off Deliverables

  • Soil analysis report
  • Inspection report
  • Ready-to-move house with agreed requirements
  • Keys to doors and locks
  • Safety and warranty documents for all installed components
  • Final cost report and relevant receipts
  • Copy of final signed-off contract

Milestones

Milestones are any deliverables, vital events, or achievements throughout the project lifecycle (PMBOK 2008). Selection of milestone should be such that it ensures completion of a major stage in a project. This gives a sequential movement to a project progress and easy slide into the next stage. Efficient selection of milestones simplifies documentation and project planning activities.

Table 4: Milestones

Serial number  Milestone  Completion date 
1 Completion of initial activities 14 November 2019
2 Completion of foundation work 04 Dec 2019
3 Completion of external work 03 Jan 2020
4 Completion of internal work  20 March 2020
5 Completion of installation of appliances and fittings  10 April 2020
6 Completion of final inspection and closure  16 April 2020

External Dependencies 

External factors or parties that influence the project performance during project life cycle are called the external dependencies. Such dependencies are not in control by the project manager but plans can be developed to efficiently manage them.

  1. Regulatory bodies for legal clearance and approvals.
  2. Unfavourable climate conditions.
  3. Material and resource availability as per project plans.
  4. Financial requirements from the client
  5. Supplier conformance to project agreements

Limits and Exclusion 

The project is being carried out to fit the calculated budget. Any change or additional services to be added aren’t considered. Suppose the customer wants add facilities such as a garden, pool or fencing, they are of excess cost outside the spending plan. These constraints would limit the ability of project managers to make decision.

We have identified a few constraints below

  1. Financial constraints as per initial agreement
  2. Design constraints as per approved plan
  3. Material and resource availability constraints as per customer specifications and budget.

4 Work Breakdown Structure (WBS) 

Background 

Larson et al. (2013, p. 113) defines WBS as a hierarchical technique that sequentially bifurcates the project at hand into smaller parts. WBS gives overall outline of the whole project and aids project managers to identify all work elements of the project. Hierarchical breakdown provides basis for project managers to control and monitor project progress with respect deadlines or milestones. 

Successful completion Jones Villa project within specified time requires the visualisation of the project into work elements. This visualisation is given the WBS. Therefore, formation of WBS is curial part of this project and every element requires a cost and time estimation. WBS forms the basis for project planning, budgeting and scheduling. Finally, we can efficiently track our going cost and performance with respect to actual cost and deadlines using WBS. (Refer Appendix 4)

Hierarchy

Table 5: WBS Coding

WBS Code Name Description
1 Initial Activities Basic activities that are required to be completed before starting to build the house. 
1.1 Project Workflow Planning Documenting the project plan
1.2 Regulatory Body Approvals Getting the approval from government or other regulatory body to proceed with the project execution
1.3 Team Formation Forming a team required to run the project effectively with responsibilities
1.4 Risk Assessment Identifying any potential risk associated with the project and relevant action plan
1.5 Initial Meeting Open meeting with client, community members and other involved parties
2 Foundation Work Activities related to laying foundation work
2.1 Site Clearing Clearing the plot for building house
2.2 Soil Analysis Analysing the soil to plan the resource required to build a house
2.3 Creating Channels Based on the layout plan required channels are created on the foundation area. 
2.4 Laying Vapour barrier Vapour barrier sheet is placed on the foundation area to avoid soil moisture transfer to concrete slab 
2.5 Laying Reinforced Bars Reinforced bars are placed in the channels 
2.6 Laying Fine Mesh Fine mesh is placed on the foundation area to lock the concrete and prevent little cracks 
2.7 Installing Plumbing facilities Initial plumbing work like connection to drainage and water source. 
2.8 Initial Electrical Work Initial electrical work required like earthing and power source connection are made 
2.9 Pouring Concrete Concrete is poured on the foundation area and even distribution of concrete is ensured at this stage
3 External Work All activities related to construction of outer framework
3.1 Frame Construction Exterior wooden framework for the house
3.2 Roof Trusses Construction Installation of roof trusses
3.3 Roof Work Roof tiles are placed at this stage 
4 Internal Work All Activities related to interior part of the house
4.1 Electrical Work Electrical wiring
4.2 Plumbing Work Installing water and other plumbing connections
4.3 Insulation work R3.5 rated insulations to the walls
4.4 Plastering Plastering the framework to prepare for brick laying
4.5 Laying clay bricks Laying the bricks according to the planned house structure
4.6 Installation of Internal Doors Installing the doors with locks that are inside the house
4.7 Painting Painting the walls and ceiling
4.8 Water proofing Waterproofing the wet areas like bathroom, kitchen and laundry room
4.9 Tile Work Paying tiles after waterproofing the areas
4.10 Carpenter work All the wooden furnishing inside the house
4.11 Installation of External Doors Installing main front and back doors
5 Appliances and fittings Installing all electrical appliances along with client approved fittings
5.1 Kitchen Tasks related to kitchen area
5.1.1 Installing kitchen appliances Appliances are fitted as per plan
5.1.2 Polished Sink Installation of the sink
5.1.3 Taps Taps are fitted
5.1.4 Kitchen Shelfs and cupboards Shelfs and cupboards are placed
5.2 Laundry & Bathroom Laundry and bathroom fittings are done
5.2.1 Laundry tub Laundry tub is fitted
5.2.2 Tap wear Taps and other are placed
5.2.3 Washing machine connections and Dryer Washing machine and a dryer are connected
5.2.4 Shower and screen Shower fittings are done along with placing screens
5.2.5 Toilet suits Installation of Coroma toilet suits with dual flush capacity
5.2.6 Holders and vanity stand Holders for purposes such as toilet rolls, soap holders, and cabinets are fitted
6 Final Closure Last few checks to ensure adherence to initial plans
6.1 Inspection Final inspection carried out
6.2 Handover Review Report and Keys Final report and keys are handed over to the owners
6.3 Signoff Meeting Meeting to finish the project proposal

5 Network Diagram

Background

Network diagram are used in project management for visual representation of all the sequential and dependent activities within the project. The relationship between the activities is represented by arrows and nodes. Network diagrams are mainly used because it is helpful in reaching project’s goal effectively, by working on duration of project and finding its critical path. (Battersby, A., 1970)

Advantages of using network diagrams are:

  • It helps to validate the estimation of time duration of project.
  • It aids in planning, organising and controlling.
  • It provides opportunities where we can compress the schedule of the project.

It is important for our project because it will help us to find the critical path of our project and we can keep track on the project is it going according to the schedule or not. It will help us to justify the estimation of time for the project.

Network Diagram

Network diagram is made by listing major activities, with its predecessor and successor activities. We can know the early finish, early start, late start, late finish of the activities. From the help of the network we can find free float and total float of the activities. The activities with zero total float give us the critical path of the network diagram. Activities on critical path can’t be delayed otherwise it will affect whole duration of the project. (Refer Appendix 3)

Gantt Chart

Gantt chart shows the schedule of project in form of a chart. It shows start and end time for different activities, the duration of activities, predecessors of the activities, activities which are overlapping each other and the start and end time of the project. (Refer Appendix 2)

The critical path for our project observed from the Gantt chart is 1<2<3<4<5<66

6 Risk Management

Background and rationale

Risk is associated with the uncertainty of the future, and it can have a positive or negative effect on the event of interest. Risk management is vital part of project management, and it is ongoing process. So, there should be risk management at every stage of the project. Risk is made up of two parts such as consequence and probability. By understanding the level of severity of the risk will assist project managers better plan to mitigate effects and keep the project on track. We are going to focus the negative risks associated with the project that can have negative effect on the project and delay its progress. Since risks will have a negative effect on the objectives of project and will lead to having dissatisfied customers and will hamper the success of business of any organisation. Therefore, risk management is important part of the project.

Brainstorming the level of severity and the occurrence of the risk will be giving a reference to rank risks in level of importance. Based on the level of importance we will prepare a plan to mitigate and prepare appropriate plan. Also, all relevant risks are communicated to all interested stakeholders and top management. Overall risk management will improve the process knowledge and communication of the involved parties and give a systematic framework to address new risks encountered in an ongoing project.

Risk Register

The risk register identifies all the risks associated with the project at every stage from initiation to project sign off. And gives framework control the uncertainty of future on the project objectives. This report identifies all the risks associated with construction of the house. We have taken into account all the risks that are having risk level such as low, moderate, high and significant. The risk register is divided into six sections such as finance, technical, external, internal, safety and environmental. After completing the risk assessment, we have identified six significant risks, six high risks, nine moderate risks, and seven low risks.

Table 6: Likelihood description

Level Likelihood Explanation
1 Rare Happens only rare situations
2 Unlikely Happens but not anticipated
3 Possible May happen
4 Likely Probably happens in most situations
5 Almost certain Expected to happen in most situations

Table 7: Consequence description

Level Consequence Explanation
1 Insignificant Very less impact on the project objectives
2 Minor Minor impact on the project objectives
3 Moderate Moderate impact on the project objectives
4 Major Major impact on the project objectives
5 Catastrophic Stops the project for significant amount of time

Table 8: Risk matrix


Consequences
Insignificant (1) Minor (2) Moderate (3) Major (4) Catastrophic (5)



Likelihood
Rare (1) 1 2 3 4 5
Unlikely (2) 2 4 6 8 10
Possible (3) 3 6 9 12 15
Likely (4) 4 8 12 16 20
Almost certain (5) 5 10 15 20 25

Low risk = 1-4

Moderate risk = 5-6

High risk = 8-10

Significant risk = 12-25

Table 9: Risk register

Ref Risk associated with the event The consequences of an event happening Controls Rating Level of risk Risk priority
Likelihood (L) Consequences (C) (L) (C)
Risk related to finance
1 Material cost increase Likely Major Additional 10% cost consideration during budget calculation 4 4 16 Significant
2 Increase in tax Possible Moderate Additional consideration given in the budget 3 3 9 High
Risk related to technical aspects
3 Design inaccuracy Rare Catastrophic Design verification stage 1 5 5 Moderate
4 Improper site assessment Unlikely Major Hiring through verified source 2 4 8 High
5 Equipment breakdown Unlikely Moderate Adherence to preventative maintenance plan 2 3 6 Moderate
6 Unavailability of material Unlikely Moderate Safety stock planned 2 3 6 Moderate
7 Lack of availability of machines Unlikely Moderate Selecting suppliers with good delivery ratings 2 3 6 Moderate
8 Task stoppage due to unavailability of transport facility Unlikely Moderate Using agencies with excellent ratings 2 3 6 Moderate
9 Failure of structure units Rare Major Maintaining adherence to design plans 1 4 4 Low
10 Mishandling of waste materials Possible Minor Setting standard procedures for handling 3 2 6 Moderate
Internal risks
11 Disagreement between stakeholders Possible Major Proper communication channels setup 3 4 12 Significant
12 Communication system not effective Likely Major Feedback taken from interested parties 4 4 16 Significant
13 Employee disagreement Possible Moderate Daily meeting to address issues 3 3 9 High
14 Worker productivity reduction Unlikely Moderate Regular assessment and training sessions planned 2 3 6 Moderate
15 Excessive interference of the owner in design Unlikely Minor Explaining standard working procedures and contract requirements during initiation 2 2 4 Low
16 Inexperienced staff selection Possible Moderate Induction, training and regular assessment planned 3 3 9 High
17 Workers/ Staff unplanned leave Possible Moderate All unplanned leave will be communicated to project manager directly 3 3 9 High
External risks
18 Environmental regulation violation Possible Moderate Adherence to environmental regulation 3 3 9 High
19 External party involvement
Unlikely
Major Confidential agreement signed with all involved parties 1 4 4 Low
20 Failure of suppliers Unlikely Major All suppliers selected after assessment of their performance and facility 1 4 4 Low
21 No power Unlikely Major Backup power supply equipment hired 1 4 4 Low
22 Communication failure Unlikely Major All staff and workers were insisted to use Telstra network connection to avoid disruption 1 4 4 Low
23 Local regulatory unwanted interference Rare Major Ensuring strict compliance with regulatory guidelines 1 4 4 Low
Safety risks
24 Injury of workers due to fall Likely Moderate Proper protective guards provided 4 3 12 Significant
25 Injury to visitors Likely Moderate Proper protective guards provided to visitors. 4 3 12 Significant
26 Injury to public Likely Moderate Construction barrier constructed to limit public access to main gates. 4 3 12 Significant
27 Fire Rare Catastrophic Adequate resources provide to handle and avoid fire incidents 1 5 5 Moderate
Environmental risks
28 Rain Likely Major Allowance to rainy days in overall plan 4 4 16 Significant
29 Flood Likely Major Drainage system established 4 4 16 Significant
30 Bush Fire Likely Major Awareness provided about risk related to bush fire 4 4 16 Significant
31 Natural calamities Rare Catastrophic Insurance 1 5 5 Moderate

Risk Treatment Plan

In the risk treatment plan, we address the significant and high identified at the risk identification stage. And we have decided not to give additional action for low and moderate risk. Since controls currently available can mitigate the risks arising from these sources.

Table 10: Risk treatment plan

The risk in priority order from risk register Possible risk treatment options Preferred options Risk rating after treatment Result of cost benefit analysis A – Accept B – Reject Person responsible for implementation of option Timetable for implementation How will this risk and the treatment options be monitored?
Material cost increase – Additional 10% cost consideration during the budget calculation. – Pre agreement with all suppliers to freeze the prices. -Buying all stock required at the beginning of the project. Pre -agreement with all suppliers to freeze the prices.
Low A Project manager Initial stage -Internal and external audits. -Verification of supplier agreement by the sourcing team
Disagreement between stakeholders – Proper communication channels setup. -Regular review meeting with relevant stakeholders Regular review meeting with relevant stakeholders Low A Project manager & supervisor The ongoing process through the project Regular feedback is taken by stakeholders
Communication system not effective – Feedback taken from interested parties -Project progress report sent weekly through mail Project progress report send weekly through mail Low A Supervisor Weekly Feedback taken by interested parties
Injury of workers due to fall – Proper protective guards provided – The proper path set in the worksite to walk around without obstacle Proper path set in the worksite to walk around without obstacle Low A Project Manager Initial Daily inspection of work layout and safety features.
Injury to visitors -Protective wear provided before entering the site. -Induction provided to increase awareness about safety measures. Induction provided to increase awareness about safety measures. Low A Site Supervisor As per requirement Visitor register will be maintained at the entrance gate
Injury to public -A barrier constructed around the construction area to restrict public access. Barrier constructed around the construction area to restrict public access. Low A Project Manager Once Measures are going to be implemented during risk assessment stage under initial activities
Rain -Allowance to rainy days in the overall plan Allowance to rainy days in the overall plan Low A Project Manager Through the project Verification of project timeline on a regular basis
Bush Fire -Awareness provided related to the risk associated with bush fire. -All safety measures and guidelines are given by midcoast council implementation All safety measures and guidelines are given by midcoast council implementation Low A Project Manager Once Measures are going to be implemented during risk assessment stage under initial activities
Flood -Drainage system established -Back up pumps set up to pump water out Back up pumps set up to pump water out Low A Project Manager Through the project Layout verification stage
Increase in tax – Additional consideration is given in the budget. -Pre agreement set up with the owner to review cost of project with respect to tax Pre agreement set up with the owner to review cost of project with respect to tax Low A Project Manager Initial Verification of project documents at before the agreement
Improper site assessment – Hiring through the verified source -Verification of data by second party Verification of data by the second part Low A Design Engineer Design stage Design verification stage introduced
Inexperienced staff selection – Induction, training and regular assessment planned -Hiring staff on contract basis to assess skills Hiring staff on contract basis to assess skills Low A Project Manager Human resource hiring stage Regular skill assessment
Workers/ Staff unplanned leave -Training provided to all staff and workers to take responsibility of other job roles in case of unplanned leave. – Additional casual staff and workers hired to act as a back up Additional casual staff and workers hired to act as a back up Low A Project Manager Project planning stage
Consideration given in team forming stage.
Environmental regulation violation – Adherence to environmental regulation -Check points introduced daily workplace inspection Check points introduced daily workplace inspection Low A Supervisor On going Internal and external audits

7 Histogram of Resources

Background

A resource in project management includes the materials, labor, tools, and equipment needed to complete the project. As a project manager we should ensure that the resources are available when they are needed materials. Histogram of Resources is an important component of project management which can ensure project is executed according to the work breakdown structure (WBS). A resource Management plan can help to arrange all the human and non-human resources according to the time schedules and budgets, and keep records of important data like quantity of resources, constraints etc.

Human Resource List

The human Resources are listed below according to the WBS

Table 11: Human Resource List

Activity Role/Task Description Human Resource Name Maximum Units Constraint
1.1 Project Workflow Planning Clients, Project Manager 3 Budget, Time
1.2 Regulatory Body Approval Government Agency 1 Design, Environment, Safety
1.3 Team Format Project Manager, Engineers 3 Shift Planning, Employee Scheduling
1.4 Risk Assessments Project Manager, Engineers 3 Experience, Lack of Data
1.5 Initial Meeting Clients, Project Manager, Engineers 5 Availability
2.1 Site Clearing HR/HC truck driver 2 Technical, Time, Availability
Excavator operator 2
Bulldozer driver 2
Labours 6
2.2 Soil Analysis Geotechnical Consultant 1 Availability
2.3 Creating Channels Engineer 1 Technical, Resources
Labours 6
2.4 Laying vapour barrier Labours 6 Time
2.5 Laying reinforcement bars Engineer 1 Time, Resources
Reinforcing iron workers 5
2.6 Laying fine mesh Rigger 4 Schedule, Technical
Welder 2
Machine operator 2
2.7 Installing plumbing Engineer 1 Budget, Technical
Plumber 5
2.8 Initial electric work Electrician 4 Technical, Time
2.9 Pouring concrete Concrete workers 7 Infrastructure, Time
3.1 Frame Construction Form workers 8 Quality, Time
Labours 12
3.2 Roof Trusses Construction Labours 7 Quality, Time
3.3 Roof Work Labours 10 Quality, Time
4.1 Electric work Electrician 2 Technical
4.2 Plumbing work Plumber 5 Technical
4.3 Insulation work Labours 6 Technical
4.4 Plastering Labour 8 Quality
4.5 Laying Bricks Bricklayers 14 Quality, Time
4.6 Installation of internal doors Doors and windows installers 2 Quality, Technical
4.7 Painting Painter 6 Quality, Budget
4.8 Water Proofing Labours 8 Technical
4.9 Tile Work Labours 5 Time, Resources
4.10 Carpenter Work Carpenter 7 Quality, Resources
4.11 Installation of external doors Doors and Windows Installer 2 Quality, Budget
5.1.1 Installing Kitchen Appliances Carpenter 2 Quality, Budget
Interior Decorator 1
5.1.2 Polished Sink Labour 2 Resource
5.1.3 Taps Labour 2 Resource
5.1.4 Kitchen shelfs and cupboard Labour 4 Resource
5.2.1 Laundry Tub Labour 2 Budget
5.2.2 Tap Wear Labour 2 Budget
5.2.3 Washing Machine Connection and Dryer Technician 1 Budget
5.2.4 Shower and Screen Bathroom Fitters 2 Budget
5.2.5 Toilet Suits Bathroom fitters 2 Quality, Budget
5.2.6 Holders and Vanity Stand Bathroom fitters 2 Budget
6.1 Inspection Project Manager 1 Quality, Budget, Schedule
Client 2
Engineer 2
6.2 Handover Review Report and Keys Clients 2 Risk Tolerance, Budget, Technical
Project Manager 1
6.3 Signoff Meeting Clients 2 Schedule
Project Manager 1

Resource Levelling (Human Resource)

Resource levelling is the concept which ensures the most efficient utilization of resources needed for completing a project according to the limited availability. From the resource list mentioned above, we can see the number of human resources needed to complete each of the sub activities. It is not practical to assume that all the resources will be available at a time when they require to complete all of these sub activities and that is why we have chosen to level the number of labours to be levelled.

A table is given bellow identifying activities 2.1 to 2.9 from the WBS as activities A to I which will be levelled.

Table 12: Activities to be levelled

Activity Predecessor Duration (Days) Number of Human/Day
A (2.1) 1 12
B (2.2) 2 1
C (2.3) A, B 2 7
D (2.4) C 1 6
E (2.5) D 2 6
F (2.6) E 1 8
G (2.7) F 2 6
H (2.8) F 2 4
I (2.9) G, H 1 7

Considering each activity’s starting and completion date from the Gantt chart, the table below shows the total number of human resources needed each day, from Day 1 to Day 11.

Table 13: Human resources needed

Activity










A 12









B 1 1








C

7 7






D



6





E




6 6



F






8


G







6 6
H







4 4
I









7
Days 1 2 3 4 5 6 7 8 9 10 11
Human Resource 13 5 7 7 6 6 6 8 10 10 7

Now if we set the constraint that we cannot use more than 10 labours per day in our project to save the labour cost, we can see that only Day 1 consumes more than 10 labours per day. But the activity C depends on A and B so allocating activity A anywhere else will cause the project to take more time. Hence the only way to level activity A’s resource is to use half of the human resources and complete in two days instead of one. That means, we will use one truck driver, one excavator operator, one bulldozer operator, and only three labours for the site clearing activity per day.

Therefore, the overallocation of human resource has been levelled as below.

Table 14: After levelling of Human Resource

Activity










A 6 6








B 1 1








C

7 7






D



6





E




6 6



F






8


G







6 6
H







4 4
I









7
Days 1 2 3 4 5 6 7 8 9 10 11
Human Resource 7 7 7 7 6 6 6 8 10 10 7

Non-Human Resource List

The non-human Resources are listed below according to the WBS

Table 15: Non-Human Resource List

Activity Task Description Non-Human Resources Name Unit Constraint
1.1 Project Work Flow Planning Computer 1 Budget
1.2 Regulatory Body Approval Design 1 Time
1.3 Team Formation Stationary 1 Availability
1.4 Risk Assessments Computer 1 Methodology
1.5 Initial Meeting Computer 1 Schedule
2.1 Site Clearing Loppers 10 Budget
Pruners 8
Hand saws 12
Shovels, 14
Pickaxes 6
Rakes 16
Hoes 6
Excavator 1
Bulldozer 1
Dump Trucks, 2
2.2 Soil Analysis Testing Laboratory 1 Availability
2.3 Creating Channels Stump Cutter 8 Budget
Drainage installation tools 5
Shovels 15
Spades 8
2.4 Laying vapour barrier Vapour retarder 180-meter square Procurement
Covering 50 mm
Coating 12 Litre
2.5 Laying reinforcement bars Concrete 700 Kg Quality, Budget
Steel 5 Ton
Safety Gear 16
2.6 Laying fine mesh Wire mesh 200 kg Budget
Concrete Slab 24*24 meter
Welding Machine 2
2.7 Installing Plumbing Facilities Design 1 Quality, Budget
Pipes 200 meters
Fittings 150
Valves 50
2.8 Initial electric work Circuit design 1 Budget, Availability
Generator 1
Switch Board 25
Voltage regulator 4
Inverter 15
2.9 Pouring concrete Concrete mixer 2 Procurement, Time
Safety boots 20 Pairs
Gloves 20
Shovels 10
Levels 10
Safety Glasses 20
3.1 Frame Construction Timber 200 Kg Resource, Time
Plywood 100 Kg
Hammer 15
Measuring tools 18
Chainsaw 7
Hand Saw 12
3.2 Roof Trusses Construction Thread cutting machines 2 Budget
J bolts 70
3.3 Roof Work Measuring Tools 12 Time
Cements 200 Kg
4.1 Electric Work Lights 22 Budget
Storage Battery 4
Exhaust Fans 6
Switch Board 12
Alarm systems 1
Smoke detectors 20
4.2 Plumbing Work Pipes 200 m Quality, Time
Pump 6
Plumbing Tools 4
4.3 Insulation work Insulator 400 feet Quality
Stripping Tools 4
4.4 Plastering Plasters 50 kg Quality, Budget
Trowel 15
Measuring tools 4
Buckets 14
4.5 Laying Clay Bricks Bricks 15000 Time, Quality, Safety







Cements 400 kg
Trowels 15
Shovels 12
Gauges 7
Levels 10
Bolsters 12
Buckets 25
4.6 Installation of Internal Doors Bolts 50 Quality
Doors 15
Measuring tools 4
Lock Kits 14
4.7 Painting Paint 40 Buckets Customer Satisfaction,
Brush 20
4.8 Water Proofing Plywood 200 Piece Safety, Time
Coating 80 L
4.9 Tile Work Tiles 80 Boxes Resources, Budget. Time
Mallets 12
Tile Saw 8
4.10 Carpenter Work Wood 60 Kg Procurement, Time
Saw 16
Shaper 7
4.11 Installation of External Doors Doors 6 Time
Installation kits 2
5.1.1 Installing Kitchen Appliances Stoves 2 Procurement, Quality
Drill Machines 4
5.1.2 Polished Sink Sink 2 Budget, Time
Drill Machines 3
Fitting 6
5.1.3 Taps Water Tap 4 Procurement, Budget, Quality
Pipe Fittings 6
Drill Machines 5
5.1.4 Kitchen Shelfs and Cupboards Cup Board 2 Budget, Customer Satisfaction
Cabinets 4
Nuts and Bolts 22
Drill Machines 4
5.2.1 Laundry Tub Tub 2 Budget, Customer Satisfaction
Drying Rack 4
Drill Machines 3
5.2.2 Tap Wear Tap 6 Procurement, Budget
Fitting 8
Drill Machines 4
5.2.3 Washing Machine Connectors and Dryer Washing Machine 1 Time, Budget
Dryer 1
Wire 20 m
Drill Machines 3
5.2.4 Bathroom work Shower Fitting 6 Budget, Customer Satisfaction
Drill Machines 2
5.2.5 Toilet Suits Toilet Suit 4 Budget
Plumbing Fitting 16
Nuts and Bolts 28
Drill Machines 6
5.2.6 Holders and Vanity Stands Holders 8 Procurement, Budget
Vanity Stands 4
Screws 20
Screw Divers 8
Drill Machines 6
6.1 Quality Inspection Design 1 Safety, Resources, Quality
Inspection Tools 12
6.2 Handover Review Report and Keys Design 1 Schedule, Resources
Budget 1
Resource List 1
Daily Reports 120
6.3 Signoff Meeting Computers 2 Schedule, Customer Satisfaction
Reports 1
Design 1

Resource Levelling (Non-Human Resource)

We can see from the table above that drill machines are needed for all of the activities from 5.1.1 to 5.2.6. So we have chosen this non-human resource to be levelled considering the limitation that we cannot have more than 8 drill machines per day due to the limited number of resources we have purchased.

The table below identifies activity 5.1.1 to 5.2.3 as A to G and shows the predecessor, duration and number of drill machine required to complete each of these activities.

Table 16: Activities to be levelled

Activity Predecessor Duration (Days) Number of Drill Machines/Day
A 5 4
B 2 3
C B 3 5
D C 3 4
E C 1 3
F C 2 4
G F 3 3

Considering each activity’s starting and completion date from the Gantt chart, the table below shows the total number of human resources needed each day, from Day 1 to Day 10.

Table 17: Non-human resources needed each day

Activity









A 4 4 4 4





B 2 2







C

5 5





D



4 4 4


E




3



F





4 4

G






3 4 4
Days 1 2 3 4 5 6 7 8 9 10
Drill Machines 6 6 9 9 4 7 8 7 4 4

From the tables and chart given above, we can see that day 3 and day 4 we will need more drill machine that we have. As activity A is not the predecessor of neither B and C, we can allocate half of the activities at the end of table with activity G to complete A as below.

Table 18: After levelling of non-human resources

Activity









A 4 4





4 4
B 2 2







C

5 5





D



4 4 4


E




3



F





4 4

G






3 4 4
Days 1 2 3 4 5 6 7 8 9 10
Drill Machines 6 6 5 5 4 7 8 7 8 8

After levelling the resource, it can be seen from the chart that the utilization of the drill machine has been levelled according to the availability without enhancing the project duration.

8 Cost

Background

The estimation of costing is essential to predict finances and resources which are necessary to complete the project within the defined scope. Estimations account the individual elements of the project which constitute to the overall budget. Costs are generally divided into two types- direct and indirect costs. Direct costs are departmental or confined to a specific area of the project such as equipment, labour and materials. Indirect costs are those costs which are not accountable directly to the project such as overhead charges, and costs related to administration and personnel.

Cost summary

The below table depicts the overall cost breakdown including direct and indirect costs along with the margin percentage.

Table 19: Cost Table Summary

Direct project cost $ 756,698.26
Overhead cost (20% of project cost) $ 151,339.65
Estimated cost $ 908,037.91
Profit margin (20% of estimated cost) $ 181,607.58
Total project cost $ 1,089,645.49

S-Curve

S-curve depicts cumulative costs or quantities against time. It shows the progression with respect to time. The below S-curve represents the cost of the project with respect to time.

Cost table

Table 20: Cost Table

Description Type Unit Quantity Unit price Total Reference
Clay Bricks Material Number 1,250 0.49 612.5 Austral Bricks, 2019
Concrete Material 20kg bag 180 8 1,440 Bunnings, 2019
Window locks Material Pack of 4 3 33.5 105 Bunnings, 2019
Sliding door locks Material Number 2 49.5 99 Bunnings, 2019
Roof tiles Material Sq-m 300 35.6 10,680 Rawlinson’s Australian Construction Handbook, 2013
Downpipes Material 1.8m 10 28 280 Rawlinson’s Australian Construction Handbook, 2013
Windows Material Sq-m 12 244 2,928 Rawlinson’s Australian Construction Handbook, 2013
Gainsborough “Governor” Lockset Material Number 2 39 78 Bunnings, 2019
Doors Material Number 12 350 4,200 Rawlinson’s Australian Construction Handbook, 2013
Glasswool R3.5 Insulation Material Sq-m 30 6.48 194.4 Buy Insulation Online, 2019
Wool R1.5 Insulation Material Sq-m 175 3.65 368.75 Buy Insulation Online, 2019
Timber skirting 42mm Material 5.4m 40 7.5 300 Bunnings, 2019
External wall framework Material Sq-m 252.74 55.6 14,052.34 Rawlinson’s Australian Construction Handbook, 2013
Wooden sheets Material Sq-m 180 60 10,800 Rawlinson’s Australian Construction Handbook, 2013
Door framework Material Number 12 102 1224 Rawlinson’s Australian Construction Handbook, 2013
Waterproofing Material Sq-m 40 200 8,000 Rawlinson’s Australian Construction Handbook, 2013
Floor tiles Material Sq-m 25 113 2,825 Rawlinson’s Australian Construction Handbook, 2013
Garage doors Material Number 2 700 1,400 Rawlinson’s Australian Construction Handbook, 2013
Roof truss Material Sq-m 252.74 40.7 10,286.52 Rawlinson’s Australian Construction Handbook, 2013
Metal fascia Material Sq-m 252.74 10 2,527.4 Bunnings, 2019
Barge boards Material Number 50 10 500 Rawlinson’s Australian Construction Handbook, 2013
Electrical wiring set Material Number 1 5,000 5,000 Rawlinson’s Australian Construction Handbook, 2013
Switches Material Number 30 92 2,760 Bunnings, 2019
Safe switch for refrigerator Material Number 1 75 75 Bunnings, 2019
Lamps and bulbs Material Number 32 50 1,600 Bunnings, 2019
Electric oven Material Number 1 490 490 Omega Australia, 2019
Electric Cook top Material Number 1 395 395 Omega Australia, 2019
Recirculating rangehood Material Number 1 279 279 Omega Australia, 2019
Smoke detectors Material Number 4 18 72 Bunnings, 2019
Rheem 400l electric water heater Material Number 1 1,600 1,600 Hot Water Systems, 2019
Chimney Material Number 1 200 200 Rawlinson’s Australian Construction Handbook, 2013
Wash basin Material Number 3 500 1,500 Rawlinson’s Australian Construction Handbook, 2013
Kitchen sink Material Number 1 850 850 Rawlinson’s Australian Construction Handbook, 2013
Toilet seats Material Number 2 2,020 4,040 Rawlinson’s Australian Construction Handbook, 2013
Bath tub Material Number 1 1,215 1,215 Rawlinson’s Australian Construction Handbook, 2013
Taps Material Number 6 380 2,280 Bunnings, 2019
Washing machine Material Number 1 800 800 Bunnings, 2019
Mirrors Material Number 8 130 1,040 Rawlinson’s Australian Construction Handbook, 2013
Paint Material Sq-m 1,000 25.7 25,700 Rawlinson’s Australian Construction Handbook, 2013
French polish Material Sq-m 300 52.7 15,810 Rawlinson’s Australian Construction Handbook, 2013
Project Manager Labour No. of hours 1,000 60 60,000 Rawlinson’s Australian Construction Handbook, 2013
Engineer Labour No. of hours 3750 40 150,000 Rawlinson’s Australian Construction Handbook, 2013
Architect Labour No. of hours 100 30 3,000 Rawlinson’s Australian Construction Handbook, 2013
Contractor Labour No. of hours 1,340 25 33,500 Rawlinson’s Australian Construction Handbook, 2013
Electrician Labour No. of hours 112 70 7,840 Rawlinson’s Australian Construction Handbook, 2013
Plumber Labour No. of hours 176 70 12,320 Rawlinson’s Australian Construction Handbook, 2013
Painter Labour No. of hours 480 27 12,960 Rawlinson’s Australian Construction Handbook, 2013
General labour Labour No. of hours 4500 62 297,600 Rawlinson’s Australian Construction Handbook, 2013
Tile labour Labour No. of hours 540 60 32,400 Rawlinson’s Australian Construction Handbook, 2013
Brick layers Labour No. of hours 640 65 41,600 Rawlinson’s Australian Construction Handbook, 2013

All costs mentioned are in Australian Dollars (AUD$)

Cumulative Cost Table

Table 21: Cumulative cost table

Code Description W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21
1 Initial Activities




















1.1 Project work flow planning 7,200



















1.2 Regulatory body approvals
1,000


















1.3 Team formation




















1.4 Risk Assessment
2,880


















1.5 Initial meeting
800


















2 Foundation work




















2.1 Site clearing

1,984

















2.2 Soil analysis

2,500

















2.3 Creating channels

13,888

















2.4 Laying vapour barrier

6,944

















2.5 Laying reinforced bars


13,888
















2.6 Laying fine mesh


6,944
















2.7 Installing plumbing facilities


3,360
















2.8 Initial electrical work


2,240
















2.9 Pouring concrete


6,944
















3 External work




















3.1 Frame construction



41,746.17 34,802.17














3.2 Roof trusses construction




17,230.52 34,720 20,832












3.3 Roof work






19,478 19,478











4 Internal work




















4.1 Electrical work







4,740 10,295










4.2 Plumbing work








2,240 5,600 2,240








4.3 Insulation work










21,126 28,145







4.4 Plastering work











6,944 20,832






4.5 Laying clay bricks












14,560 36,400 29,120




4.6 Installation of internal doors














11,480




4.7 Painting














5,400 5,400



4.8 Waterproofing














6,480 6,480



4.9 Tile work















30,601



4.10 Carpenter work















17,944 35,944


4.11 Installation of external doors
















8,344


5 Appliances and fitting




















5.1 Kitchen




















5.1.1 Installing kitchen appliance
















37,247.4


5.1.2 Polished sink
















19,202


5.1.3 Taps
















20,832


5.1.4 Kitchen shelves and cupboards
















20,832


5.2 Laundry and bathroom




















5.2.1 Laundry tub

















6,944

5.2.2 Tap wear

















13,888

5.2.3 Washing machine connection and dryer

















28,832

5.2.4 Shower and screen


















27,776
5.2.5 Toilet suits


















26,087
5.2.6 Holders and vanity stands


















6,944
6 Final closure




















6.1 Inspection



















8,480
6.2 Handover review report and keys



















480
6.3 Sign off meeting



















480
Total cost
7,200 4,680 12,816 15,376 41,746.17 52,032.69 34,720 40,310 24,218 12,535 5,600 23,366 35,089 35,392 36,400 52,480 60,425 142,401.4 49,664 60,807 9,440
Accumulated cost
7,200 11,880 24,696 40,072 81,818.17 133,850.86 168,570.86 208,880.86 233,098.86 245,633.86 251,233.86 274,599.86 309,688.86 345,080.86 381,480.86 433,960.86 495,385.86 636,787.26 686,451.26 747,258.26 756,698.26

All costs mentioned are in Australian Dollars (AUD$)

References

Austral Bricks 2019, viewed 11 October 2019, <https://australbricks.com.au/nsw/price-list/>

Boddy, D. & Paton, R. 2004, ‘Responding to competing narratives: Lessons for project managers’, International Journal of Project Management, vol. 22, pp. 225-33.  

Bunnings, 2019, viewed 11 October 2019, <www.bunnings.com.au>

Freeman, R. E. 1984, Strategic management: a stakeholder approach, Boston : Pitman.   

Gibson, K. 2000, ‘The moral basis of stakeholder theory’, Journal of Business Ethics, vol. 26, no. 3, pp. 245-57. 

Hot Water Systems. viewed 11 October 2019, <https://www.samedayhotwaterservice.com.au>

Larson, E.W., Hoing, B., Gray, C. F., Dantin, U. & Baccarini, D. 2013, Project management: the managerial process, McGraw-Hill Education Pty Ltd, Australia. 

Rawlinsons Australian Construction Handbook 2013, 31st edn, Rawlinsons Publishing, Perth, Western Australia.

Appendix

Appendix 1: Version Control

Date Document Version Authors Changes made
01/08/2019 Stakeholder 0.1 Group 29 Background and rationale added
02/08/2019 Stakeholder 0.2 Group 29 Prioritisation grid and Communication plan added
07/08/2019 Scope and WBS 0.3 Group 29 Background and rationale added
10/08/2019 Scope and WBS 0.4 Group 29 Objectives, Assumptions, Goals, In-scope and out of scope work, and deliverables
11/08/2019 Scope and WBS 0.5 Group 29 WBS added
15/08/2019 Network Diagram 0.6
Background, Rationale and network diagram added
17/08/2019 Network Diagram 0.7 Group 29 Gantt chart
13/09/2019 Risk 0.8
Risk background and rationale added
14/09/2019 Risk 0.9
Risk register created
15/09/2019 Risk 1.0
Risk register updated
16/09/2019 Risk 1.1
Risk Treatment plan created
21/09/2019 Histograms 1.2
Background and rationale added
22/09/2019 Histogram 1.3
Human and non-human list added
28/09/2019 Cost 1.4
Cost background and rationale added
29/09/2019 Cost 1.5
Cost summary and cumulative cost table with S-curve
01/10/2019 Stakeholder 1.6
Stakeholder section updated according to feedback
03/10/2019 Scope and WBS 1.7
Updated according to feedback
05/10/2019 Network Diagram 1.8
Diagrams created using Microsoft Projects
06/09/2019 Risk 1.9
Additional risk identified and changed made according to feedback
08/09/2019 Histograms 2.0
Levelling and histograms are created and added
10/09/2019 Cost 2.1
Cost table with updated S-curve added
11/09/2019 Cost 2.2
Final changes made for submission

Appendix 2: Gantt Chart

Appendix 3: Network Diagram

Appendix 4: WBS diagram

The post 49002 Managing Projects – Assignment 2 appeared first on My Assignment Online.

WhatsApp
Hello! Need help with your assignments?

For faster services, inquiry about  new assignments submission or  follow ups on your assignments please text us/call us on +1 (251) 265-5102

Submit Your Questions to Writers for FREE!!

X
GET YOUR PAPER DONE