Faculty of Engineering & Information Technology
49002 Managing Projects – Assignment 2
49002 Managing Projects COVER SHEET for Final Report of Group ASSIGNMENT | ||
By signing this form and submitting the attached report, I certify that this assignment is my and group members own work, based on our personal study and/or research, and we have acknowledged all material and sources in the preparation of the assignment. We all certify that the assignment has not previously been submitted for assessment in any other course or at any other time in the same course and that we have not copied in part or whole or other-wise plagiarized work of others. We all agree and accept the % contribution of each member of the group as listed below. | ||
Group Number 29 | Date 11/10/2019 | |
13420219 | Mohan Sai Santosh Ayyala | |
13395001 | Rowin D’souza | |
13662933 | Rushi Dadhania | |
13666336 | Sarbartha Goswami | |
13682683 | Shravani Priya |
Date submitted: 11/10/2019
Document Version: 2.2
Table of Contents
1 Introduction 5
Overview 5
Key Milestones 5
2 Stakeholder 6
Background 6
Stakeholder register 6
Stakeholder prioritisation grid 8
Stakeholder Communication Plan 10
3 Scope Statement 12
Background and rationale 12
Objectives, Goals, Needs 12
Assumptions 13
In-scope work and Out-of-scope work 14
In-Scope work 14
Out-of-Scope work 14
Deliverable 15
Milestones 15
External Dependencies 16
Limits and Exclusion 16
4 Work Breakdown Structure (WBS) 17
Background 17
Hierarchy 17
5 Network Diagram 20
Background 20
Network Diagram 20
Gantt Chart 20
6 Risk Management 21
Background and rationale 21
Risk Register 21
Risk Treatment Plan 26
7 Histogram of Resources 30
Background 30
Human Resource List 30
Resource Levelling (Human Resource) 32
Non-Human Resource List 35
Resource Levelling (Non-Human Resource) 40
8 Cost 43
Background 43
Cost summary 43
S-Curve 43
Cost table 44
Cumulative Cost Table 47
References 48
Appendix 48
Appendix 1: Version Control 48
Appendix 2: Gantt Chart 50
Appendix 3: Network Diagram 51
Appendix 4: WBS diagram 52
List of tables
Table 1: Stakeholder Register
Table 2: Stakeholder power and interest matrix
Table 3: Stakeholder Communication Plan
Table 4: Milestones
Table 5: WBS Coding
Table 6: Likelihood description
Table 7: Consequence description
Table 8: Risk Matrix
Table 9: Risk Register
Table 10: Risk Treatment Plan
Table 11: Human Resource List
Table 12: Human activities to be levelled
Table 13: Human resources needed each day
Table 14: After levelling of human Resources
Table 15: Non-Human Resource List
Table 16: Non-Human activities to be levelled
Table 17: Non-human resources needed each day
Table 18: After Levelling of non-human resources
Table 19: Cost table summary
Table 20: Cost Table
Table 21: Cumulative Cost Table
1 Introduction
This report is a proposal for our project management plan for constructing a house for the Jones family in Forster, NSW. Our Blue Bricks consultancy very interested in taking up the project and provide quality services to our client. The project is proposed to be completed within approximately twenty-one weeks and the estimated cost of the project is 1,088,645.49 AUD.
The knowledge areas mentioned in Project Management Book of Knowledge (PMBoK) were considered while developing this project plan report. This document is a reference to how to execute to the plan and will act as a validation sheet for cross checking.
Overview
Project Start Date: 28th October 2019
Project End Date: 16th April 2020
Total cost of the project: $ 1,089,645.49
Key Milestones
The key milestones are as follows:
- Completion of initial activities
- Completion of foundation work
- Completion of external work
- Completion of internal work
- Completion of installation of appliances and fitting
- Completion of final inspection and closure
2 Stakeholder
Background
Managing projects comprises of numerous roles out of which stakeholder management is one the most important aspects. Project management involves planning, organizing, delegating and controlling throughout the project lifecycle including managing involved parties with a stake. Stakeholders are defined as “Any group or individual who can affect or is affected by the achievement of the organizations objectives” (Freeman 1984, p. 46). Stakeholders will directly or indirectly affect the progress of the project, where the affect can be either positive or negative in nature. Implications include cost overruns, more lead time for project completion and may lead to project failure.
“Stakeholders are individuals, groups or institutions with an interest in the project, and who can affect the outcome” (Boddy and Paton 2004). Any skilled person, operational or managerial, that is involved with the project requirements could affect the development process. Interest of some stakeholders are in line with the organisation’s goals. On the other hand, interests of some stakeholders are not in line with organisation’s goals. In conclusion, stakeholders play curial role in the success or failure of an organisation (Gibson 2000).
Stakeholder register
A project manager needs to create and maintain a record of all the stakeholders to efficiently keep track of the project. The project manager needs to ensure the progress is in line with the stakeholder’s requirements. It is crucial to discuss the requirements of each stakeholder before executing the project and keep a record based on priority and influence. The stakeholder register for our project provides basic information and tells about the type of each stakeholder.
Table 1: Stakeholder Register
ID Information | Assessment Information | Classification | ||||
Stakeholder name/ position | Contact | Role in project | Major requirements/ expectation | Potential influence | Internal/External | Supporter/Neutral/ Resistor |
Mr and Mrs Jones | Email ID |
Customer | Handover of project within agreed time, cost and high quality. | Maximum | Internal | Supporter |
Mid-Coast Council | Council@midcoast.nsw.gov.au | Local regulatory authority | Maintaining conformance to the approved design plans during construction and planning of the project. | Maximum | External | Neutral |
Designer |
Email ID |
Designer | Conformance to approved design plans. – Timely communication of any design change requirement before implementation. | Moderate | Internal | Neutral |
Stakeholder name/ position | Contact | Role in Project | Major Requirement | Potential Influence | Internal / External | Supporter/Neutral/Resistor |
Bank | Email ID | Financer | Completion of project within agreed budget. | Moderate | External | Supporter |
Helen Aitken | Helen.Aitken@uts.edu.au | Consultant | Clear and on time communication about the task with all relevant information about the required documents. | Minimal | Internal | Neutral |
Labour contractor | Email ID |
Labour contractor | Effective management of manpower to support construction activity to reduce project delay time. | Moderate | Internal | Supporter |
Plumber | Email ID |
Plumber | Completion and start of the work within agreed time. | Moderate | Internal | Neutral |
Electrician | Email ID | Electrician | Completion and start of the work within agreed time. | Moderate | Internal | Neutral |
Painter | Email ID | Painter | Completion and start of the work within agreed time. | Moderate | Internal | Neutral |
Supplier | Email ID |
Supplier | Supply of correct quantity and conformance to delivery schedule. | Minimal | External | Neutral |
Local Community | In Person Meetings | Neighbours | Completion of work within disturbance to the local community and reduction of noise, dust and undesirable effects from the construction activities. | Minimal | External | Neutral |
Stakeholder prioritisation grid
Stakeholder priortisation grid is needed to be created because it is very important to classify stakeholder according to their power and interest in the project. The agenda of each stakeholder is different is so their decision-making power. The power and interest matrix identifies and differentiates the value of each stakeholder based on ratings (1-5). The stakeholder with minimum interest and power is rated ‘1’ and stakeholders with highest interest and power are rated ‘5’.
The grid is further classified into four quadrants which shows the classification of stakeholders according to their power and interest. stakeholders who needs to be monitor is shown in the bottom left quadrant as they have less interest and power in the project. In upper left quadrant shows the stakeholders who needs to be kept satisfied as they have high power and less interest in the project. The stakeholders in bottom right quadrant has less interest and power but they are need kept informed as they are important for project. Upper right quadrant shows stakeholders who needs to be manage closely as they have more power and interest in the project. This grid helps the project manager to develop a communication method and maintain effective communication based on importance.
No. | Stakeholder | Power (1-5) | Interest (1-5) |
1 | Customer | 5 | 5 |
2 | Local Regulatory Body | 4 | 2 |
3 | Designer | 3 | 4 |
4 | Financer | 4 | 3 |
5 | Consultant | 1 | 3 |
6 | Labour Contractor | 4 | 3 |
7 | Plumber | 3 | 2 |
8 | Electrician | 3 | 2 |
9 | Painter | 2 | 2 |
10 | Supplier | 2 | 1 |
11 | Local Community | 1 | 1 |
Table 2: Stakeholder Power and Interest Matrix
Figure 1: Stakeholder Power and Interest Grid
Stakeholder Communication Plan
Stakeholder Communication Plan is based on stakeholder prioritisation plan. It is a table that tells the communication strategy corresponding to each stakeholder.
Table 3: Stakeholder Communication Plan
SR. No. | Communication Type | Description | Frequency | Format | Involved Parties | Action Plan | Responsible Individual |
1 | Initial meeting | Discussion with local community regarding project. | Once | Face to Face meeting | Project Manager, Neighbours | Register the concerns | Project manager |
2 |
Task Monitoring |
Discussion of completed, pending, and future tasks | Weekly | In Person/ Conference Call/ Email | Project manager, Department Representatives | Update Project Status | Project manager |
3 | Community Announcements | Intimating local community about any changes in project plan | As per requirement | Face to Face meeting | Project Manager, Neighbours | Register the concerns | Project manager |
4 | Team Meeting | Discussion of project status and further plan of action | Weekly | In person or conference call | Project manager, Department Representatives | Updating status register, and Requirements | Project manager |
5 | Resource Requirement Meeting | Comparison of various supplier quotes and price negotiation | Once with individual vendor | In person / mail / conference call |
Procurement Head, Suppliers | Finalising quotes and generating invoices | Project manager and Procurement Head |
6 | Change-point Meeting | Discussion of unplanned changes | As per requirement | In Person / Conference Call | Project manager, Department Representatives | Updating status register | Project manager |
7 | Site meeting | Discussion of activity related with site members | As per requirement | In person | Site supervisor | Discussion of work instruction and inspection sheet | Site supervisor and Project manager |
8 | Task Progress Report | Workflow monitoring and modification | Daily | In Person / on call | Site supervisor | Tracking Project Progress | Project manager |
9 | Task Progress Report | Workflow monitoring and modification | Daily | In Person/Telephone | Project Manager | Summarized report | Consultant |
10 | Overall Task Progress Report | Workflow monitoring and modification | Every last working day of the week | Project Manager | Collecting information and documentation | Mr and Mrs Jones, Helen Aitken |
3 Scope Statement
Background and rationale
Project scope clearly gives an understanding of the end stage or result of our project (Larson et al. 2013) and the purpose of this activity is to define the project face to end-users and create a project plan accordingly. Scope management of the project refers to the processes which will make sure a project’s scope is defined and mapped accurate. It further has methods which will assign proper amount of work necessary to effectively complete a project, also concerned with controlling what is part of project’s scope or not. The scope of our project is to properly bifurcate the tasks which are part of the project and which are not, along with scheduling the tasks according to the milestones giving it specific deadline to complete the project in the given duration.
Scope management is a vital activity that should be carried out by every project manager to avoid confusion among stakeholders and eliminate project delays. Clearly defining the scope will ensure quality and cost effectiveness of all the activities related to project management.
The scope statement for the Jones villa project will identify goals, deliverables, milestones, technical requirements, limitations and exclusions. This can be used as a reference to any modifications, inclusions, and exclusions from the project. Not having a well-defined scope can lead to many problems like miscommunication, delays in deliverables, increase in cost or possible failure to complete project.
Objectives, Goals, Needs
The main objective of our project is to construct a house which is fulfilling all the requirements of the owner in the given time and budget allocated to the project. In addition, it will be built according to the Australian Building code. The objectives clearly identify and quantify the resources required, skilled or unskilled labour and basis for overall construction along with interdependent activities and timely completion of the tasks.
The following are our goals
- Build a house of 252.74 m2 area in Forster Grange, NSW, Australia. Forster is in one of the precincts under the mid-coast council.
- Develop a project proposal considering the lump sum amount set by the Jones family.
- Design a roof trusses type house with 3m high walls and windows 2.1m x 0.9m.
- Design and build a house which confirms to external and internal requirements provided by the clients.
- Procure all the kitchen, bathroom, laundry and any electrical appliances as mentioned by the client during the agreement and planning stage.
- Ensure safety and quality inspections at every stage to ensure overall quality of the project.
- Handover the fully completed and inspected house within the projected time frame along with the review report.
Assumptions
An Assumption is something that is considered by default without any evidence. In an ideal case during project planning, all the information related to project phases is available before hand and project manager can make accurate predictions related to health of the project. Although, this may not be true for real world scenarios. Project managers need to fix certain variable like cost related to resources, manpower and scheduling. Project management team can get a better understanding of risk associated with the project by brainstorming assumptions that are relevant. Also the impact related to not confirming to the assumptions can be analysed beforehand and action plans can be created to mitigate the effects.
Assumptions can be good or bad depending on the affect they have on the project. It is always better to clarify or recheck with the clients and other involved parties to avoid any confusion or mismanagement. Impacts of these assumptions not holding true are categorised into four categories such as low, medium, high, and severe.
The following are the assumptions made during developing the project proposal
- The technical and non-technical specifications do not change during project execution (Impact level: High)
- The scope defined during project initiation stage does not change throughout the project lifecycle (Impact level: High).
- Cost related to the project and stakeholders would be paid and reimbursed as per project plan and agreements (Impact level: Medium).
- The resources for house construction would be procured as per project schedule (Impact level: High).
- Skilled and unskilled manpower would be assigned as per project needs to avoid excessive costs or delays (Impact level: Medium).
- Rules and regulations set by the mid-coast council do not change throughout the project lifecycle (Impact level: Low)
- There will be no interruption in project workflow by weather conditions, natural calamities like floods, bushfire during execution stage (Impact level: Severe).
- A well organised guidelines and systems for waste management from the construction site is already set up and in action. (Impact level: medium)
- We already have a clearance certificate from the government to build the house. (Impact level: Low)
In-scope work and Out-of-scope work
Setting boundaries for any project is a vital part of the project management. This boundary differentiates work into two categories such as in-scope and out-0f-scope work. Identification of these categories assists project managers to focus or direct their resources into relevant activities. Moreover, this helps in eliminating resource utilisation for unrelated activities.
In-Scope work
- Assessing and examining the plot for soil properties related to construction within the Forster Grange.
- Getting approvals and legal clearance from the local regulatory bodies.
- Performing site preparation, levelling or fill-up for constructions for initial foundation work.
- Setting up provisions for electrical and plumbing work during the foundation stage.
- Construction of external framework and clay brickwork along with roof trusses as per approved plan requirement.
- Ordering resources and arranging manpower, raw materials for construction activities as per agreed plan.
- Arranging necessities for construction such as electricity and water.
- Pre and post inspection of in-house work and subcontracted work to ensure conformance to the approved plan.
- Installation of “Gainsborough” keyed locks for front and rear doors along with security locks for other doors and windows.
- Constructing internal structure and furnishing as per agreement with the clients.
Out-of-Scope work
- Drafting layout plan and floor heightening
- Designing and setting up Air-conditioning system
- Landscaping activities like gardening and swimming pool construction
- Building a boundary or fence around the plot.
Deliverable
Deliverables are documents/necessities that are essential for keeping the client updated throughout the execution of project. Deliverables can be classified into two categories such as recurring deliverables and sign-off deliverables. Recurring deliverables are the ones used as a basis for measuring and controlling the progress of project outcomes like activities, or milestones. These are periodically submitted to the client or the relevant parties. Sigh-off deliverables are documents or amenities that are agreed upon by the client during the initial contract and are to be submitted only once.
Recurring Deliverables
- Layout drawings and documents
- Site analysis report
- Regulatory body approval documents
- Invoices for the resources
- Status report of the progress in the project
Sign-off Deliverables
- Soil analysis report
- Inspection report
- Ready-to-move house with agreed requirements
- Keys to doors and locks
- Safety and warranty documents for all installed components
- Final cost report and relevant receipts
- Copy of final signed-off contract
Milestones
Milestones are any deliverables, vital events, or achievements throughout the project lifecycle (PMBOK 2008). Selection of milestone should be such that it ensures completion of a major stage in a project. This gives a sequential movement to a project progress and easy slide into the next stage. Efficient selection of milestones simplifies documentation and project planning activities.
Table 4: Milestones
Serial number | Milestone | Completion date |
1 | Completion of initial activities | 14 November 2019 |
2 | Completion of foundation work | 04 Dec 2019 |
3 | Completion of external work | 03 Jan 2020 |
4 | Completion of internal work | 20 March 2020 |
5 | Completion of installation of appliances and fittings | 10 April 2020 |
6 | Completion of final inspection and closure | 16 April 2020 |
External Dependencies
External factors or parties that influence the project performance during project life cycle are called the external dependencies. Such dependencies are not in control by the project manager but plans can be developed to efficiently manage them.
- Regulatory bodies for legal clearance and approvals.
- Unfavourable climate conditions.
- Material and resource availability as per project plans.
- Financial requirements from the client
- Supplier conformance to project agreements
Limits and Exclusion
The project is being carried out to fit the calculated budget. Any change or additional services to be added aren’t considered. Suppose the customer wants add facilities such as a garden, pool or fencing, they are of excess cost outside the spending plan. These constraints would limit the ability of project managers to make decision.
We have identified a few constraints below
- Financial constraints as per initial agreement
- Design constraints as per approved plan
- Material and resource availability constraints as per customer specifications and budget.
4 Work Breakdown Structure (WBS)
Background
Larson et al. (2013, p. 113) defines WBS as a hierarchical technique that sequentially bifurcates the project at hand into smaller parts. WBS gives overall outline of the whole project and aids project managers to identify all work elements of the project. Hierarchical breakdown provides basis for project managers to control and monitor project progress with respect deadlines or milestones.
Successful completion Jones Villa project within specified time requires the visualisation of the project into work elements. This visualisation is given the WBS. Therefore, formation of WBS is curial part of this project and every element requires a cost and time estimation. WBS forms the basis for project planning, budgeting and scheduling. Finally, we can efficiently track our going cost and performance with respect to actual cost and deadlines using WBS. (Refer Appendix 4)
Hierarchy
Table 5: WBS Coding
WBS Code | Name | Description |
1 | Initial Activities | Basic activities that are required to be completed before starting to build the house. |
1.1 | Project Workflow Planning | Documenting the project plan |
1.2 | Regulatory Body Approvals | Getting the approval from government or other regulatory body to proceed with the project execution |
1.3 | Team Formation | Forming a team required to run the project effectively with responsibilities |
1.4 | Risk Assessment | Identifying any potential risk associated with the project and relevant action plan |
1.5 | Initial Meeting | Open meeting with client, community members and other involved parties |
2 | Foundation Work | Activities related to laying foundation work |
2.1 | Site Clearing | Clearing the plot for building house |
2.2 | Soil Analysis | Analysing the soil to plan the resource required to build a house |
2.3 | Creating Channels | Based on the layout plan required channels are created on the foundation area. |
2.4 | Laying Vapour barrier | Vapour barrier sheet is placed on the foundation area to avoid soil moisture transfer to concrete slab |
2.5 | Laying Reinforced Bars | Reinforced bars are placed in the channels |
2.6 | Laying Fine Mesh | Fine mesh is placed on the foundation area to lock the concrete and prevent little cracks |
2.7 | Installing Plumbing facilities | Initial plumbing work like connection to drainage and water source. |
2.8 | Initial Electrical Work | Initial electrical work required like earthing and power source connection are made |
2.9 | Pouring Concrete | Concrete is poured on the foundation area and even distribution of concrete is ensured at this stage |
3 | External Work | All activities related to construction of outer framework |
3.1 | Frame Construction | Exterior wooden framework for the house |
3.2 | Roof Trusses Construction | Installation of roof trusses |
3.3 | Roof Work | Roof tiles are placed at this stage |
4 | Internal Work | All Activities related to interior part of the house |
4.1 | Electrical Work | Electrical wiring |
4.2 | Plumbing Work | Installing water and other plumbing connections |
4.3 | Insulation work | R3.5 rated insulations to the walls |
4.4 | Plastering | Plastering the framework to prepare for brick laying |
4.5 | Laying clay bricks | Laying the bricks according to the planned house structure |
4.6 | Installation of Internal Doors | Installing the doors with locks that are inside the house |
4.7 | Painting | Painting the walls and ceiling |
4.8 | Water proofing | Waterproofing the wet areas like bathroom, kitchen and laundry room |
4.9 | Tile Work | Paying tiles after waterproofing the areas |
4.10 | Carpenter work | All the wooden furnishing inside the house |
4.11 | Installation of External Doors | Installing main front and back doors |
5 | Appliances and fittings | Installing all electrical appliances along with client approved fittings |
5.1 | Kitchen | Tasks related to kitchen area |
5.1.1 | Installing kitchen appliances | Appliances are fitted as per plan |
5.1.2 | Polished Sink | Installation of the sink |
5.1.3 | Taps | Taps are fitted |
5.1.4 | Kitchen Shelfs and cupboards | Shelfs and cupboards are placed |
5.2 | Laundry & Bathroom | Laundry and bathroom fittings are done |
5.2.1 | Laundry tub | Laundry tub is fitted |
5.2.2 | Tap wear | Taps and other are placed |
5.2.3 | Washing machine connections and Dryer | Washing machine and a dryer are connected |
5.2.4 | Shower and screen | Shower fittings are done along with placing screens |
5.2.5 | Toilet suits | Installation of Coroma toilet suits with dual flush capacity |
5.2.6 | Holders and vanity stand | Holders for purposes such as toilet rolls, soap holders, and cabinets are fitted |
6 | Final Closure | Last few checks to ensure adherence to initial plans |
6.1 | Inspection | Final inspection carried out |
6.2 | Handover Review Report and Keys | Final report and keys are handed over to the owners |
6.3 | Signoff Meeting | Meeting to finish the project proposal |
5 Network Diagram
Background
Network diagram are used in project management for visual representation of all the sequential and dependent activities within the project. The relationship between the activities is represented by arrows and nodes. Network diagrams are mainly used because it is helpful in reaching project’s goal effectively, by working on duration of project and finding its critical path. (Battersby, A., 1970)
Advantages of using network diagrams are:
- It helps to validate the estimation of time duration of project.
- It aids in planning, organising and controlling.
- It provides opportunities where we can compress the schedule of the project.
It is important for our project because it will help us to find the critical path of our project and we can keep track on the project is it going according to the schedule or not. It will help us to justify the estimation of time for the project.
Network Diagram
Network diagram is made by listing major activities, with its predecessor and successor activities. We can know the early finish, early start, late start, late finish of the activities. From the help of the network we can find free float and total float of the activities. The activities with zero total float give us the critical path of the network diagram. Activities on critical path can’t be delayed otherwise it will affect whole duration of the project. (Refer Appendix 3)
Gantt Chart
Gantt chart shows the schedule of project in form of a chart. It shows start and end time for different activities, the duration of activities, predecessors of the activities, activities which are overlapping each other and the start and end time of the project. (Refer Appendix 2)
The critical path for our project observed from the Gantt chart is 1<2<3<4<5<66
6 Risk Management
Background and rationale
Risk is associated with the uncertainty of the future, and it can have a positive or negative effect on the event of interest. Risk management is vital part of project management, and it is ongoing process. So, there should be risk management at every stage of the project. Risk is made up of two parts such as consequence and probability. By understanding the level of severity of the risk will assist project managers better plan to mitigate effects and keep the project on track. We are going to focus the negative risks associated with the project that can have negative effect on the project and delay its progress. Since risks will have a negative effect on the objectives of project and will lead to having dissatisfied customers and will hamper the success of business of any organisation. Therefore, risk management is important part of the project.
Brainstorming the level of severity and the occurrence of the risk will be giving a reference to rank risks in level of importance. Based on the level of importance we will prepare a plan to mitigate and prepare appropriate plan. Also, all relevant risks are communicated to all interested stakeholders and top management. Overall risk management will improve the process knowledge and communication of the involved parties and give a systematic framework to address new risks encountered in an ongoing project.
Risk Register
The risk register identifies all the risks associated with the project at every stage from initiation to project sign off. And gives framework control the uncertainty of future on the project objectives. This report identifies all the risks associated with construction of the house. We have taken into account all the risks that are having risk level such as low, moderate, high and significant. The risk register is divided into six sections such as finance, technical, external, internal, safety and environmental. After completing the risk assessment, we have identified six significant risks, six high risks, nine moderate risks, and seven low risks.
Table 6: Likelihood description
Level | Likelihood | Explanation |
1 | Rare | Happens only rare situations |
2 | Unlikely | Happens but not anticipated |
3 | Possible | May happen |
4 | Likely | Probably happens in most situations |
5 | Almost certain | Expected to happen in most situations |
Table 7: Consequence description
Level | Consequence | Explanation |
1 | Insignificant | Very less impact on the project objectives |
2 | Minor | Minor impact on the project objectives |
3 | Moderate | Moderate impact on the project objectives |
4 | Major | Major impact on the project objectives |
5 | Catastrophic | Stops the project for significant amount of time |
Table 8: Risk matrix
Consequences | ||||||
Insignificant (1) | Minor (2) | Moderate (3) | Major (4) | Catastrophic (5) | ||
Likelihood |
Rare (1) | 1 | 2 | 3 | 4 | 5 |
Unlikely (2) | 2 | 4 | 6 | 8 | 10 | |
Possible (3) | 3 | 6 | 9 | 12 | 15 | |
Likely (4) | 4 | 8 | 12 | 16 | 20 | |
Almost certain (5) | 5 | 10 | 15 | 20 | 25 |
Low risk = 1-4
Moderate risk = 5-6
High risk = 8-10
Significant risk = 12-25
Table 9: Risk register
Ref | Risk associated with the event | The consequences of an event happening | Controls | Rating | Level of risk | Risk priority | ||
Likelihood (L) | Consequences (C) | (L) | (C) | |||||
Risk related to finance | ||||||||
1 | Material cost increase | Likely | Major | Additional 10% cost consideration during budget calculation | 4 | 4 | 16 | Significant |
2 | Increase in tax | Possible | Moderate | Additional consideration given in the budget | 3 | 3 | 9 | High |
Risk related to technical aspects | ||||||||
3 | Design inaccuracy | Rare | Catastrophic | Design verification stage | 1 | 5 | 5 | Moderate |
4 | Improper site assessment | Unlikely | Major | Hiring through verified source | 2 | 4 | 8 | High |
5 | Equipment breakdown | Unlikely | Moderate | Adherence to preventative maintenance plan | 2 | 3 | 6 | Moderate |
6 | Unavailability of material | Unlikely | Moderate | Safety stock planned | 2 | 3 | 6 | Moderate |
7 | Lack of availability of machines | Unlikely | Moderate | Selecting suppliers with good delivery ratings | 2 | 3 | 6 | Moderate |
8 | Task stoppage due to unavailability of transport facility | Unlikely | Moderate | Using agencies with excellent ratings | 2 | 3 | 6 | Moderate |
9 | Failure of structure units | Rare | Major | Maintaining adherence to design plans | 1 | 4 | 4 | Low |
10 | Mishandling of waste materials | Possible | Minor | Setting standard procedures for handling | 3 | 2 | 6 | Moderate |
Internal risks | ||||||||
11 | Disagreement between stakeholders | Possible | Major | Proper communication channels setup | 3 | 4 | 12 | Significant |
12 | Communication system not effective | Likely | Major | Feedback taken from interested parties | 4 | 4 | 16 | Significant |
13 | Employee disagreement | Possible | Moderate | Daily meeting to address issues | 3 | 3 | 9 | High |
14 | Worker productivity reduction | Unlikely | Moderate | Regular assessment and training sessions planned | 2 | 3 | 6 | Moderate |
15 | Excessive interference of the owner in design | Unlikely | Minor | Explaining standard working procedures and contract requirements during initiation | 2 | 2 | 4 | Low |
16 | Inexperienced staff selection | Possible | Moderate | Induction, training and regular assessment planned | 3 | 3 | 9 | High |
17 | Workers/ Staff unplanned leave | Possible | Moderate | All unplanned leave will be communicated to project manager directly | 3 | 3 | 9 | High |
External risks | ||||||||
18 | Environmental regulation violation | Possible | Moderate | Adherence to environmental regulation | 3 | 3 | 9 | High |
19 | External party involvement |
Unlikely |
Major | Confidential agreement signed with all involved parties | 1 | 4 | 4 | Low |
20 | Failure of suppliers | Unlikely | Major | All suppliers selected after assessment of their performance and facility | 1 | 4 | 4 | Low |
21 | No power | Unlikely | Major | Backup power supply equipment hired | 1 | 4 | 4 | Low |
22 | Communication failure | Unlikely | Major | All staff and workers were insisted to use Telstra network connection to avoid disruption | 1 | 4 | 4 | Low |
23 | Local regulatory unwanted interference | Rare | Major | Ensuring strict compliance with regulatory guidelines | 1 | 4 | 4 | Low |
Safety risks | ||||||||
24 | Injury of workers due to fall | Likely | Moderate | Proper protective guards provided | 4 | 3 | 12 | Significant |
25 | Injury to visitors | Likely | Moderate | Proper protective guards provided to visitors. | 4 | 3 | 12 | Significant |
26 | Injury to public | Likely | Moderate | Construction barrier constructed to limit public access to main gates. | 4 | 3 | 12 | Significant |
27 | Fire | Rare | Catastrophic | Adequate resources provide to handle and avoid fire incidents | 1 | 5 | 5 | Moderate |
Environmental risks | ||||||||
28 | Rain | Likely | Major | Allowance to rainy days in overall plan | 4 | 4 | 16 | Significant |
29 | Flood | Likely | Major | Drainage system established | 4 | 4 | 16 | Significant |
30 | Bush Fire | Likely | Major | Awareness provided about risk related to bush fire | 4 | 4 | 16 | Significant |
31 | Natural calamities | Rare | Catastrophic | Insurance | 1 | 5 | 5 | Moderate |
Risk Treatment Plan
In the risk treatment plan, we address the significant and high identified at the risk identification stage. And we have decided not to give additional action for low and moderate risk. Since controls currently available can mitigate the risks arising from these sources.
Table 10: Risk treatment plan
The risk in priority order from risk register | Possible risk treatment options | Preferred options | Risk rating after treatment | Result of cost benefit analysis A – Accept B – Reject | Person responsible for implementation of option | Timetable for implementation | How will this risk and the treatment options be monitored? |
Material cost increase | – Additional 10% cost consideration during the budget calculation. – Pre agreement with all suppliers to freeze the prices. -Buying all stock required at the beginning of the project. | Pre -agreement with all suppliers to freeze the prices. |
Low | A | Project manager | Initial stage | -Internal and external audits. -Verification of supplier agreement by the sourcing team |
Disagreement between stakeholders | – Proper communication channels setup. -Regular review meeting with relevant stakeholders | Regular review meeting with relevant stakeholders | Low | A | Project manager & supervisor | The ongoing process through the project | Regular feedback is taken by stakeholders |
Communication system not effective | – Feedback taken from interested parties -Project progress report sent weekly through mail | Project progress report send weekly through mail | Low | A | Supervisor | Weekly | Feedback taken by interested parties |
Injury of workers due to fall | – Proper protective guards provided – The proper path set in the worksite to walk around without obstacle | Proper path set in the worksite to walk around without obstacle | Low | A | Project Manager | Initial | Daily inspection of work layout and safety features. |
Injury to visitors | -Protective wear provided before entering the site. -Induction provided to increase awareness about safety measures. | Induction provided to increase awareness about safety measures. | Low | A | Site Supervisor | As per requirement | Visitor register will be maintained at the entrance gate |
Injury to public | -A barrier constructed around the construction area to restrict public access. | Barrier constructed around the construction area to restrict public access. | Low | A | Project Manager | Once | Measures are going to be implemented during risk assessment stage under initial activities |
Rain | -Allowance to rainy days in the overall plan | Allowance to rainy days in the overall plan | Low | A | Project Manager | Through the project | Verification of project timeline on a regular basis |
Bush Fire | -Awareness provided related to the risk associated with bush fire. -All safety measures and guidelines are given by midcoast council implementation | All safety measures and guidelines are given by midcoast council implementation | Low | A | Project Manager | Once | Measures are going to be implemented during risk assessment stage under initial activities |
Flood | -Drainage system established -Back up pumps set up to pump water out | Back up pumps set up to pump water out | Low | A | Project Manager | Through the project | Layout verification stage |
Increase in tax | – Additional consideration is given in the budget. -Pre agreement set up with the owner to review cost of project with respect to tax | Pre agreement set up with the owner to review cost of project with respect to tax | Low | A | Project Manager | Initial | Verification of project documents at before the agreement |
Improper site assessment | – Hiring through the verified source -Verification of data by second party | Verification of data by the second part | Low | A | Design Engineer | Design stage | Design verification stage introduced |
Inexperienced staff selection | – Induction, training and regular assessment planned -Hiring staff on contract basis to assess skills | Hiring staff on contract basis to assess skills | Low | A | Project Manager | Human resource hiring stage | Regular skill assessment |
Workers/ Staff unplanned leave | -Training provided to all staff and workers to take responsibility of other job roles in case of unplanned leave. – Additional casual staff and workers hired to act as a back up | Additional casual staff and workers hired to act as a back up | Low | A | Project Manager | Project planning stage |
Consideration given in team forming stage. |
Environmental regulation violation | – Adherence to environmental regulation -Check points introduced daily workplace inspection | Check points introduced daily workplace inspection | Low | A | Supervisor | On going | Internal and external audits |
7 Histogram of Resources
Background
A resource in project management includes the materials, labor, tools, and equipment needed to complete the project. As a project manager we should ensure that the resources are available when they are needed materials. Histogram of Resources is an important component of project management which can ensure project is executed according to the work breakdown structure (WBS). A resource Management plan can help to arrange all the human and non-human resources according to the time schedules and budgets, and keep records of important data like quantity of resources, constraints etc.
Human Resource List
The human Resources are listed below according to the WBS
Table 11: Human Resource List
Activity | Role/Task Description | Human Resource Name | Maximum Units | Constraint |
1.1 | Project Workflow Planning | Clients, Project Manager | 3 | Budget, Time |
1.2 | Regulatory Body Approval | Government Agency | 1 | Design, Environment, Safety |
1.3 | Team Format | Project Manager, Engineers | 3 | Shift Planning, Employee Scheduling |
1.4 | Risk Assessments | Project Manager, Engineers | 3 | Experience, Lack of Data |
1.5 | Initial Meeting | Clients, Project Manager, Engineers | 5 | Availability |
2.1 | Site Clearing | HR/HC truck driver | 2 | Technical, Time, Availability |
Excavator operator | 2 | |||
Bulldozer driver | 2 | |||
Labours | 6 | |||
2.2 | Soil Analysis | Geotechnical Consultant | 1 | Availability |
2.3 | Creating Channels | Engineer | 1 | Technical, Resources |
Labours | 6 | |||
2.4 | Laying vapour barrier | Labours | 6 | Time |
2.5 | Laying reinforcement bars | Engineer | 1 | Time, Resources |
Reinforcing iron workers | 5 | |||
2.6 | Laying fine mesh | Rigger | 4 | Schedule, Technical |
Welder | 2 | |||
Machine operator | 2 | |||
2.7 | Installing plumbing | Engineer | 1 | Budget, Technical |
Plumber | 5 | |||
2.8 | Initial electric work | Electrician | 4 | Technical, Time |
2.9 | Pouring concrete | Concrete workers | 7 | Infrastructure, Time |
3.1 | Frame Construction | Form workers | 8 | Quality, Time |
Labours | 12 | |||
3.2 | Roof Trusses Construction | Labours | 7 | Quality, Time |
3.3 | Roof Work | Labours | 10 | Quality, Time |
4.1 | Electric work | Electrician | 2 | Technical |
4.2 | Plumbing work | Plumber | 5 | Technical |
4.3 | Insulation work | Labours | 6 | Technical |
4.4 | Plastering | Labour | 8 | Quality |
4.5 | Laying Bricks | Bricklayers | 14 | Quality, Time |
4.6 | Installation of internal doors | Doors and windows installers | 2 | Quality, Technical |
4.7 | Painting | Painter | 6 | Quality, Budget |
4.8 | Water Proofing | Labours | 8 | Technical |
4.9 | Tile Work | Labours | 5 | Time, Resources |
4.10 | Carpenter Work | Carpenter | 7 | Quality, Resources |
4.11 | Installation of external doors | Doors and Windows Installer | 2 | Quality, Budget |
5.1.1 | Installing Kitchen Appliances | Carpenter | 2 | Quality, Budget |
Interior Decorator | 1 | |||
5.1.2 | Polished Sink | Labour | 2 | Resource |
5.1.3 | Taps | Labour | 2 | Resource |
5.1.4 | Kitchen shelfs and cupboard | Labour | 4 | Resource |
5.2.1 | Laundry Tub | Labour | 2 | Budget |
5.2.2 | Tap Wear | Labour | 2 | Budget |
5.2.3 | Washing Machine Connection and Dryer | Technician | 1 | Budget |
5.2.4 | Shower and Screen | Bathroom Fitters | 2 | Budget |
5.2.5 | Toilet Suits | Bathroom fitters | 2 | Quality, Budget |
5.2.6 | Holders and Vanity Stand | Bathroom fitters | 2 | Budget |
6.1 | Inspection | Project Manager | 1 | Quality, Budget, Schedule |
Client | 2 | |||
Engineer | 2 | |||
6.2 | Handover Review Report and Keys | Clients | 2 | Risk Tolerance, Budget, Technical |
Project Manager | 1 | |||
6.3 | Signoff Meeting | Clients | 2 | Schedule |
Project Manager | 1 |
Resource Levelling (Human Resource)
Resource levelling is the concept which ensures the most efficient utilization of resources needed for completing a project according to the limited availability. From the resource list mentioned above, we can see the number of human resources needed to complete each of the sub activities. It is not practical to assume that all the resources will be available at a time when they require to complete all of these sub activities and that is why we have chosen to level the number of labours to be levelled.
A table is given bellow identifying activities 2.1 to 2.9 from the WBS as activities A to I which will be levelled.
Table 12: Activities to be levelled
Activity | Predecessor | Duration (Days) | Number of Human/Day |
A (2.1) | – | 1 | 12 |
B (2.2) | – | 2 | 1 |
C (2.3) | A, B | 2 | 7 |
D (2.4) | C | 1 | 6 |
E (2.5) | D | 2 | 6 |
F (2.6) | E | 1 | 8 |
G (2.7) | F | 2 | 6 |
H (2.8) | F | 2 | 4 |
I (2.9) | G, H | 1 | 7 |
Considering each activity’s starting and completion date from the Gantt chart, the table below shows the total number of human resources needed each day, from Day 1 to Day 11.
Table 13: Human resources needed
Activity | |||||||||||
A | 12 | ||||||||||
B | 1 | 1 | |||||||||
C | 7 | 7 | |||||||||
D | 6 | ||||||||||
E | 6 | 6 | |||||||||
F | 8 | ||||||||||
G | 6 | 6 | |||||||||
H | 4 | 4 | |||||||||
I | 7 | ||||||||||
Days | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 |
Human Resource | 13 | 5 | 7 | 7 | 6 | 6 | 6 | 8 | 10 | 10 | 7 |
Now if we set the constraint that we cannot use more than 10 labours per day in our project to save the labour cost, we can see that only Day 1 consumes more than 10 labours per day. But the activity C depends on A and B so allocating activity A anywhere else will cause the project to take more time. Hence the only way to level activity A’s resource is to use half of the human resources and complete in two days instead of one. That means, we will use one truck driver, one excavator operator, one bulldozer operator, and only three labours for the site clearing activity per day.
Therefore, the overallocation of human resource has been levelled as below.
Table 14: After levelling of Human Resource
Activity | |||||||||||
A | 6 | 6 | |||||||||
B | 1 | 1 | |||||||||
C | 7 | 7 | |||||||||
D | 6 | ||||||||||
E | 6 | 6 | |||||||||
F | 8 | ||||||||||
G | 6 | 6 | |||||||||
H | 4 | 4 | |||||||||
I | 7 | ||||||||||
Days | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 |
Human Resource | 7 | 7 | 7 | 7 | 6 | 6 | 6 | 8 | 10 | 10 | 7 |
Non-Human Resource List
The non-human Resources are listed below according to the WBS
Table 15: Non-Human Resource List
Activity | Task Description | Non-Human Resources Name | Unit | Constraint |
1.1 | Project Work Flow Planning | Computer | 1 | Budget |
1.2 | Regulatory Body Approval | Design | 1 | Time |
1.3 | Team Formation | Stationary | 1 | Availability |
1.4 | Risk Assessments | Computer | 1 | Methodology |
1.5 | Initial Meeting | Computer | 1 | Schedule |
2.1 | Site Clearing | Loppers | 10 | Budget |
Pruners | 8 | |||
Hand saws | 12 | |||
Shovels, | 14 | |||
Pickaxes | 6 | |||
Rakes | 16 | |||
Hoes | 6 | |||
Excavator | 1 | |||
Bulldozer | 1 | |||
Dump Trucks, | 2 | |||
2.2 | Soil Analysis | Testing Laboratory | 1 | Availability |
2.3 | Creating Channels | Stump Cutter | 8 | Budget |
Drainage installation tools | 5 | |||
Shovels | 15 | |||
Spades | 8 | |||
2.4 | Laying vapour barrier | Vapour retarder | 180-meter square | Procurement |
Covering | 50 mm | |||
Coating | 12 Litre | |||
2.5 | Laying reinforcement bars | Concrete | 700 Kg | Quality, Budget |
Steel | 5 Ton | |||
Safety Gear | 16 | |||
2.6 | Laying fine mesh | Wire mesh | 200 kg | Budget |
Concrete Slab | 24*24 meter | |||
Welding Machine | 2 | |||
2.7 | Installing Plumbing Facilities | Design | 1 | Quality, Budget |
Pipes | 200 meters | |||
Fittings | 150 | |||
Valves | 50 | |||
2.8 | Initial electric work | Circuit design | 1 | Budget, Availability |
Generator | 1 | |||
Switch Board | 25 | |||
Voltage regulator | 4 | |||
Inverter | 15 | |||
2.9 | Pouring concrete | Concrete mixer | 2 | Procurement, Time |
Safety boots | 20 Pairs | |||
Gloves | 20 | |||
Shovels | 10 | |||
Levels | 10 | |||
Safety Glasses | 20 | |||
3.1 | Frame Construction | Timber | 200 Kg | Resource, Time |
Plywood | 100 Kg | |||
Hammer | 15 | |||
Measuring tools | 18 | |||
Chainsaw | 7 | |||
Hand Saw | 12 | |||
3.2 | Roof Trusses Construction | Thread cutting machines | 2 | Budget |
J bolts | 70 | |||
3.3 | Roof Work | Measuring Tools | 12 | Time |
Cements | 200 Kg | |||
4.1 | Electric Work | Lights | 22 | Budget |
Storage Battery | 4 | |||
Exhaust Fans | 6 | |||
Switch Board | 12 | |||
Alarm systems | 1 | |||
Smoke detectors | 20 | |||
4.2 | Plumbing Work | Pipes | 200 m | Quality, Time |
Pump | 6 | |||
Plumbing Tools | 4 | |||
4.3 | Insulation work | Insulator | 400 feet | Quality |
Stripping Tools | 4 | |||
4.4 | Plastering | Plasters | 50 kg | Quality, Budget |
Trowel | 15 | |||
Measuring tools | 4 | |||
Buckets | 14 | |||
4.5 | Laying Clay Bricks | Bricks | 15000 | Time, Quality, Safety |
Cements | 400 kg | |||
Trowels | 15 | |||
Shovels | 12 | |||
Gauges | 7 | |||
Levels | 10 | |||
Bolsters | 12 | |||
Buckets | 25 | |||
4.6 | Installation of Internal Doors | Bolts | 50 | Quality |
Doors | 15 | |||
Measuring tools | 4 | |||
Lock Kits | 14 | |||
4.7 | Painting | Paint | 40 Buckets | Customer Satisfaction, |
Brush | 20 | |||
4.8 | Water Proofing | Plywood | 200 Piece | Safety, Time |
Coating | 80 L | |||
4.9 | Tile Work | Tiles | 80 Boxes | Resources, Budget. Time |
Mallets | 12 | |||
Tile Saw | 8 | |||
4.10 | Carpenter Work | Wood | 60 Kg | Procurement, Time |
Saw | 16 | |||
Shaper | 7 | |||
4.11 | Installation of External Doors | Doors | 6 | Time |
Installation kits | 2 | |||
5.1.1 | Installing Kitchen Appliances | Stoves | 2 | Procurement, Quality |
Drill Machines | 4 | |||
5.1.2 | Polished Sink | Sink | 2 | Budget, Time |
Drill Machines | 3 | |||
Fitting | 6 | |||
5.1.3 | Taps | Water Tap | 4 | Procurement, Budget, Quality |
Pipe Fittings | 6 | |||
Drill Machines | 5 | |||
5.1.4 | Kitchen Shelfs and Cupboards | Cup Board | 2 | Budget, Customer Satisfaction |
Cabinets | 4 | |||
Nuts and Bolts | 22 | |||
Drill Machines | 4 | |||
5.2.1 | Laundry Tub | Tub | 2 | Budget, Customer Satisfaction |
Drying Rack | 4 | |||
Drill Machines | 3 | |||
5.2.2 | Tap Wear | Tap | 6 | Procurement, Budget |
Fitting | 8 | |||
Drill Machines | 4 | |||
5.2.3 | Washing Machine Connectors and Dryer | Washing Machine | 1 | Time, Budget |
Dryer | 1 | |||
Wire | 20 m | |||
Drill Machines | 3 | |||
5.2.4 | Bathroom work | Shower Fitting | 6 | Budget, Customer Satisfaction |
Drill Machines | 2 | |||
5.2.5 | Toilet Suits | Toilet Suit | 4 | Budget |
Plumbing Fitting | 16 | |||
Nuts and Bolts | 28 | |||
Drill Machines | 6 | |||
5.2.6 | Holders and Vanity Stands | Holders | 8 | Procurement, Budget |
Vanity Stands | 4 | |||
Screws | 20 | |||
Screw Divers | 8 | |||
Drill Machines | 6 | |||
6.1 | Quality Inspection | Design | 1 | Safety, Resources, Quality |
Inspection Tools | 12 | |||
6.2 | Handover Review Report and Keys | Design | 1 | Schedule, Resources |
Budget | 1 | |||
Resource List | 1 | |||
Daily Reports | 120 | |||
6.3 | Signoff Meeting | Computers | 2 | Schedule, Customer Satisfaction |
Reports | 1 | |||
Design | 1 |
Resource Levelling (Non-Human Resource)
We can see from the table above that drill machines are needed for all of the activities from 5.1.1 to 5.2.6. So we have chosen this non-human resource to be levelled considering the limitation that we cannot have more than 8 drill machines per day due to the limited number of resources we have purchased.
The table below identifies activity 5.1.1 to 5.2.3 as A to G and shows the predecessor, duration and number of drill machine required to complete each of these activities.
Table 16: Activities to be levelled
Activity | Predecessor | Duration (Days) | Number of Drill Machines/Day |
A | – | 5 | 4 |
B | – | 2 | 3 |
C | B | 3 | 5 |
D | C | 3 | 4 |
E | C | 1 | 3 |
F | C | 2 | 4 |
G | F | 3 | 3 |
Considering each activity’s starting and completion date from the Gantt chart, the table below shows the total number of human resources needed each day, from Day 1 to Day 10.
Table 17: Non-human resources needed each day
Activity | ||||||||||
A | 4 | 4 | 4 | 4 | ||||||
B | 2 | 2 | ||||||||
C | 5 | 5 | ||||||||
D | 4 | 4 | 4 | |||||||
E | 3 | |||||||||
F | 4 | 4 | ||||||||
G | 3 | 4 | 4 | |||||||
Days | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
Drill Machines | 6 | 6 | 9 | 9 | 4 | 7 | 8 | 7 | 4 | 4 |
From the tables and chart given above, we can see that day 3 and day 4 we will need more drill machine that we have. As activity A is not the predecessor of neither B and C, we can allocate half of the activities at the end of table with activity G to complete A as below.
Table 18: After levelling of non-human resources
Activity | ||||||||||
A | 4 | 4 | 4 | 4 | ||||||
B | 2 | 2 | ||||||||
C | 5 | 5 | ||||||||
D | 4 | 4 | 4 | |||||||
E | 3 | |||||||||
F | 4 | 4 | ||||||||
G | 3 | 4 | 4 | |||||||
Days | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
Drill Machines | 6 | 6 | 5 | 5 | 4 | 7 | 8 | 7 | 8 | 8 |
After levelling the resource, it can be seen from the chart that the utilization of the drill machine has been levelled according to the availability without enhancing the project duration.
8 Cost
Background
The estimation of costing is essential to predict finances and resources which are necessary to complete the project within the defined scope. Estimations account the individual elements of the project which constitute to the overall budget. Costs are generally divided into two types- direct and indirect costs. Direct costs are departmental or confined to a specific area of the project such as equipment, labour and materials. Indirect costs are those costs which are not accountable directly to the project such as overhead charges, and costs related to administration and personnel.
Cost summary
The below table depicts the overall cost breakdown including direct and indirect costs along with the margin percentage.
Table 19: Cost Table Summary
Direct project cost | $ 756,698.26 |
Overhead cost (20% of project cost) | $ 151,339.65 |
Estimated cost | $ 908,037.91 |
Profit margin (20% of estimated cost) | $ 181,607.58 |
Total project cost | $ 1,089,645.49 |
S-Curve
S-curve depicts cumulative costs or quantities against time. It shows the progression with respect to time. The below S-curve represents the cost of the project with respect to time.
Cost table
Table 20: Cost Table
Description | Type | Unit | Quantity | Unit price | Total | Reference |
Clay Bricks | Material | Number | 1,250 | 0.49 | 612.5 | Austral Bricks, 2019 |
Concrete | Material | 20kg bag | 180 | 8 | 1,440 | Bunnings, 2019 |
Window locks | Material | Pack of 4 | 3 | 33.5 | 105 | Bunnings, 2019 |
Sliding door locks | Material | Number | 2 | 49.5 | 99 | Bunnings, 2019 |
Roof tiles | Material | Sq-m | 300 | 35.6 | 10,680 | Rawlinson’s Australian Construction Handbook, 2013 |
Downpipes | Material | 1.8m | 10 | 28 | 280 | Rawlinson’s Australian Construction Handbook, 2013 |
Windows | Material | Sq-m | 12 | 244 | 2,928 | Rawlinson’s Australian Construction Handbook, 2013 |
Gainsborough “Governor” Lockset | Material | Number | 2 | 39 | 78 | Bunnings, 2019 |
Doors | Material | Number | 12 | 350 | 4,200 | Rawlinson’s Australian Construction Handbook, 2013 |
Glasswool R3.5 Insulation | Material | Sq-m | 30 | 6.48 | 194.4 | Buy Insulation Online, 2019 |
Wool R1.5 Insulation | Material | Sq-m | 175 | 3.65 | 368.75 | Buy Insulation Online, 2019 |
Timber skirting 42mm | Material | 5.4m | 40 | 7.5 | 300 | Bunnings, 2019 |
External wall framework | Material | Sq-m | 252.74 | 55.6 | 14,052.34 | Rawlinson’s Australian Construction Handbook, 2013 |
Wooden sheets | Material | Sq-m | 180 | 60 | 10,800 | Rawlinson’s Australian Construction Handbook, 2013 |
Door framework | Material | Number | 12 | 102 | 1224 | Rawlinson’s Australian Construction Handbook, 2013 |
Waterproofing | Material | Sq-m | 40 | 200 | 8,000 | Rawlinson’s Australian Construction Handbook, 2013 |
Floor tiles | Material | Sq-m | 25 | 113 | 2,825 | Rawlinson’s Australian Construction Handbook, 2013 |
Garage doors | Material | Number | 2 | 700 | 1,400 | Rawlinson’s Australian Construction Handbook, 2013 |
Roof truss | Material | Sq-m | 252.74 | 40.7 | 10,286.52 | Rawlinson’s Australian Construction Handbook, 2013 |
Metal fascia | Material | Sq-m | 252.74 | 10 | 2,527.4 | Bunnings, 2019 |
Barge boards | Material | Number | 50 | 10 | 500 | Rawlinson’s Australian Construction Handbook, 2013 |
Electrical wiring set | Material | Number | 1 | 5,000 | 5,000 | Rawlinson’s Australian Construction Handbook, 2013 |
Switches | Material | Number | 30 | 92 | 2,760 | Bunnings, 2019 |
Safe switch for refrigerator | Material | Number | 1 | 75 | 75 | Bunnings, 2019 |
Lamps and bulbs | Material | Number | 32 | 50 | 1,600 | Bunnings, 2019 |
Electric oven | Material | Number | 1 | 490 | 490 | Omega Australia, 2019 |
Electric Cook top | Material | Number | 1 | 395 | 395 | Omega Australia, 2019 |
Recirculating rangehood | Material | Number | 1 | 279 | 279 | Omega Australia, 2019 |
Smoke detectors | Material | Number | 4 | 18 | 72 | Bunnings, 2019 |
Rheem 400l electric water heater | Material | Number | 1 | 1,600 | 1,600 | Hot Water Systems, 2019 |
Chimney | Material | Number | 1 | 200 | 200 | Rawlinson’s Australian Construction Handbook, 2013 |
Wash basin | Material | Number | 3 | 500 | 1,500 | Rawlinson’s Australian Construction Handbook, 2013 |
Kitchen sink | Material | Number | 1 | 850 | 850 | Rawlinson’s Australian Construction Handbook, 2013 |
Toilet seats | Material | Number | 2 | 2,020 | 4,040 | Rawlinson’s Australian Construction Handbook, 2013 |
Bath tub | Material | Number | 1 | 1,215 | 1,215 | Rawlinson’s Australian Construction Handbook, 2013 |
Taps | Material | Number | 6 | 380 | 2,280 | Bunnings, 2019 |
Washing machine | Material | Number | 1 | 800 | 800 | Bunnings, 2019 |
Mirrors | Material | Number | 8 | 130 | 1,040 | Rawlinson’s Australian Construction Handbook, 2013 |
Paint | Material | Sq-m | 1,000 | 25.7 | 25,700 | Rawlinson’s Australian Construction Handbook, 2013 |
French polish | Material | Sq-m | 300 | 52.7 | 15,810 | Rawlinson’s Australian Construction Handbook, 2013 |
Project Manager | Labour | No. of hours | 1,000 | 60 | 60,000 | Rawlinson’s Australian Construction Handbook, 2013 |
Engineer | Labour | No. of hours | 3750 | 40 | 150,000 | Rawlinson’s Australian Construction Handbook, 2013 |
Architect | Labour | No. of hours | 100 | 30 | 3,000 | Rawlinson’s Australian Construction Handbook, 2013 |
Contractor | Labour | No. of hours | 1,340 | 25 | 33,500 | Rawlinson’s Australian Construction Handbook, 2013 |
Electrician | Labour | No. of hours | 112 | 70 | 7,840 | Rawlinson’s Australian Construction Handbook, 2013 |
Plumber | Labour | No. of hours | 176 | 70 | 12,320 | Rawlinson’s Australian Construction Handbook, 2013 |
Painter | Labour | No. of hours | 480 | 27 | 12,960 | Rawlinson’s Australian Construction Handbook, 2013 |
General labour | Labour | No. of hours | 4500 | 62 | 297,600 | Rawlinson’s Australian Construction Handbook, 2013 |
Tile labour | Labour | No. of hours | 540 | 60 | 32,400 | Rawlinson’s Australian Construction Handbook, 2013 |
Brick layers | Labour | No. of hours | 640 | 65 | 41,600 | Rawlinson’s Australian Construction Handbook, 2013 |
All costs mentioned are in Australian Dollars (AUD$)
Cumulative Cost Table
Table 21: Cumulative cost table
Code | Description | W1 | W2 | W3 | W4 | W5 | W6 | W7 | W8 | W9 | W10 | W11 | W12 | W13 | W14 | W15 | W16 | W17 | W18 | W19 | W20 | W21 |
1 | Initial Activities | |||||||||||||||||||||
1.1 | Project work flow planning | 7,200 | ||||||||||||||||||||
1.2 | Regulatory body approvals | 1,000 | ||||||||||||||||||||
1.3 | Team formation | |||||||||||||||||||||
1.4 | Risk Assessment | 2,880 | ||||||||||||||||||||
1.5 | Initial meeting | 800 | ||||||||||||||||||||
2 | Foundation work | |||||||||||||||||||||
2.1 | Site clearing | 1,984 | ||||||||||||||||||||
2.2 | Soil analysis | 2,500 | ||||||||||||||||||||
2.3 | Creating channels | 13,888 | ||||||||||||||||||||
2.4 | Laying vapour barrier | 6,944 | ||||||||||||||||||||
2.5 | Laying reinforced bars | 13,888 | ||||||||||||||||||||
2.6 | Laying fine mesh | 6,944 | ||||||||||||||||||||
2.7 | Installing plumbing facilities | 3,360 | ||||||||||||||||||||
2.8 | Initial electrical work | 2,240 | ||||||||||||||||||||
2.9 | Pouring concrete | 6,944 | ||||||||||||||||||||
3 | External work | |||||||||||||||||||||
3.1 | Frame construction | 41,746.17 | 34,802.17 | |||||||||||||||||||
3.2 | Roof trusses construction | 17,230.52 | 34,720 | 20,832 | ||||||||||||||||||
3.3 | Roof work | 19,478 | 19,478 | |||||||||||||||||||
4 | Internal work | |||||||||||||||||||||
4.1 | Electrical work | 4,740 | 10,295 | |||||||||||||||||||
4.2 | Plumbing work | 2,240 | 5,600 | 2,240 | ||||||||||||||||||
4.3 | Insulation work | 21,126 | 28,145 | |||||||||||||||||||
4.4 | Plastering work | 6,944 | 20,832 | |||||||||||||||||||
4.5 | Laying clay bricks | 14,560 | 36,400 | 29,120 | ||||||||||||||||||
4.6 | Installation of internal doors | 11,480 | ||||||||||||||||||||
4.7 | Painting | 5,400 | 5,400 | |||||||||||||||||||
4.8 | Waterproofing | 6,480 | 6,480 | |||||||||||||||||||
4.9 | Tile work | 30,601 | ||||||||||||||||||||
4.10 | Carpenter work | 17,944 | 35,944 | |||||||||||||||||||
4.11 | Installation of external doors | 8,344 | ||||||||||||||||||||
5 | Appliances and fitting | |||||||||||||||||||||
5.1 | Kitchen | |||||||||||||||||||||
5.1.1 | Installing kitchen appliance | 37,247.4 | ||||||||||||||||||||
5.1.2 | Polished sink | 19,202 | ||||||||||||||||||||
5.1.3 | Taps | 20,832 | ||||||||||||||||||||
5.1.4 | Kitchen shelves and cupboards | 20,832 | ||||||||||||||||||||
5.2 | Laundry and bathroom | |||||||||||||||||||||
5.2.1 | Laundry tub | 6,944 | ||||||||||||||||||||
5.2.2 | Tap wear | 13,888 | ||||||||||||||||||||
5.2.3 | Washing machine connection and dryer | 28,832 | ||||||||||||||||||||
5.2.4 | Shower and screen | 27,776 | ||||||||||||||||||||
5.2.5 | Toilet suits | 26,087 | ||||||||||||||||||||
5.2.6 | Holders and vanity stands | 6,944 | ||||||||||||||||||||
6 | Final closure | |||||||||||||||||||||
6.1 | Inspection | 8,480 | ||||||||||||||||||||
6.2 | Handover review report and keys | 480 | ||||||||||||||||||||
6.3 | Sign off meeting | 480 | ||||||||||||||||||||
Total cost | 7,200 | 4,680 | 12,816 | 15,376 | 41,746.17 | 52,032.69 | 34,720 | 40,310 | 24,218 | 12,535 | 5,600 | 23,366 | 35,089 | 35,392 | 36,400 | 52,480 | 60,425 | 142,401.4 | 49,664 | 60,807 | 9,440 | |
Accumulated cost | 7,200 | 11,880 | 24,696 | 40,072 | 81,818.17 | 133,850.86 | 168,570.86 | 208,880.86 | 233,098.86 | 245,633.86 | 251,233.86 | 274,599.86 | 309,688.86 | 345,080.86 | 381,480.86 | 433,960.86 | 495,385.86 | 636,787.26 | 686,451.26 | 747,258.26 | 756,698.26 |
All costs mentioned are in Australian Dollars (AUD$)
References
Austral Bricks 2019, viewed 11 October 2019, <https://australbricks.com.au/nsw/price-list/>
Boddy, D. & Paton, R. 2004, ‘Responding to competing narratives: Lessons for project managers’, International Journal of Project Management, vol. 22, pp. 225-33.
Bunnings, 2019, viewed 11 October 2019, <www.bunnings.com.au>
Freeman, R. E. 1984, Strategic management: a stakeholder approach, Boston : Pitman.
Gibson, K. 2000, ‘The moral basis of stakeholder theory’, Journal of Business Ethics, vol. 26, no. 3, pp. 245-57.
Hot Water Systems. viewed 11 October 2019, <https://www.samedayhotwaterservice.com.au>
Larson, E.W., Hoing, B., Gray, C. F., Dantin, U. & Baccarini, D. 2013, Project management: the managerial process, McGraw-Hill Education Pty Ltd, Australia.
Rawlinsons Australian Construction Handbook 2013, 31st edn, Rawlinsons Publishing, Perth, Western Australia.
Appendix
Appendix 1: Version Control
Date | Document | Version | Authors | Changes made |
01/08/2019 | Stakeholder | 0.1 | Group 29 | Background and rationale added |
02/08/2019 | Stakeholder | 0.2 | Group 29 | Prioritisation grid and Communication plan added |
07/08/2019 | Scope and WBS | 0.3 | Group 29 | Background and rationale added |
10/08/2019 | Scope and WBS | 0.4 | Group 29 | Objectives, Assumptions, Goals, In-scope and out of scope work, and deliverables |
11/08/2019 | Scope and WBS | 0.5 | Group 29 | WBS added |
15/08/2019 | Network Diagram | 0.6 | Background, Rationale and network diagram added | |
17/08/2019 | Network Diagram | 0.7 | Group 29 | Gantt chart |
13/09/2019 | Risk | 0.8 | Risk background and rationale added | |
14/09/2019 | Risk | 0.9 | Risk register created | |
15/09/2019 | Risk | 1.0 | Risk register updated | |
16/09/2019 | Risk | 1.1 | Risk Treatment plan created | |
21/09/2019 | Histograms | 1.2 | Background and rationale added | |
22/09/2019 | Histogram | 1.3 | Human and non-human list added | |
28/09/2019 | Cost | 1.4 | Cost background and rationale added | |
29/09/2019 | Cost | 1.5 | Cost summary and cumulative cost table with S-curve | |
01/10/2019 | Stakeholder | 1.6 | Stakeholder section updated according to feedback | |
03/10/2019 | Scope and WBS | 1.7 | Updated according to feedback | |
05/10/2019 | Network Diagram | 1.8 | Diagrams created using Microsoft Projects | |
06/09/2019 | Risk | 1.9 | Additional risk identified and changed made according to feedback | |
08/09/2019 | Histograms | 2.0 | Levelling and histograms are created and added | |
10/09/2019 | Cost | 2.1 | Cost table with updated S-curve added | |
11/09/2019 | Cost | 2.2 | Final changes made for submission |
Appendix 2: Gantt Chart
Appendix 3: Network Diagram
Appendix 4: WBS diagram
The post 49002 Managing Projects – Assignment 2 appeared first on My Assignment Online.