BIM Midterm Exam
Question 1: make a simulation model for the PERT network shown in figure (1). The
time for each activity has three values as shown in brackets (minimum,
most likely, and maximum). Also, show the following information.
A) The average cycle time.
B) A histogram for 100 runs.
1
6
B
(2, 5, 14)
A
(3, 6, 15) 2
4
D
(2, 5, 8)
E 7
(3, 8, 31)
C 3
(6, 12, 30)
5
G
(3, 6, 15)
F
(5, 11, 17)
I
(3, 17, 37)
8
H
(1, 4, 7)
Figure 1: PERT network
Question 2: Figure (2) shows a flowchart of a plotting process. For this process, there
are one operator and two plotters. The operator at the beginning input
data and send it to a plotter, which takes one minute. The average times
for the two plotters to plot one project are 2 minutes and 3 minutes
respectively. After that, the operator has to cut and adjust plotted sheets,
which takes 2 minutes.
start
Input and send
data to plotters
(1′)
Plotter 1
(2′)
Plotter 2
(3′)
Cut and adjust
sheet
(2′)
Finish
Figure 2: Plotting process for each sheet.
Make a simulation model for this process that mimics 100-plotted sheets. In
your model, show the following:
a) Average cycle time and standard deviation
b) Utilization rates for all resources (operator and two plotters)