1) You are creating a customer database for the Lehigh Valley IronPigs minor league baseball
team. Draw a project network given the information below. Complete the forward and
backward pass, compute activity slack, and identify the critical path. How long will this
project take? How sensitive is the network schedule? Calculate the free slack and total slack
for all noncritical activities.
2) Considering the following project network:
a) Complete the forward and backward pass, compute activity slack, and identify the critical
path. How long will this project take?
b) Draw the project’s Gantt chart.